ASST. COMMISSIONER OF INCOME TAX, CIRCLE-16(1), HYDERABAD vs. LEO MERIDIAN INFRASTRUCTURE PROJECTS & HOTELS LIMITED, HYDERABAD

PDF · subscribers
ITA 1049/HYD/2017Status: DisposedITAT Hyderabad15 September 2022AY 2008-095 pages

In favour of the assessee: the Revenue's appeal was dismissed. From the AI summary of this appeal.

AI SummaryDismissed

What did the Tribunal hold?

The Tribunal held that the continuation of pending proceedings is prohibited once CIRP commences. All claims not part of the resolution plan are extinguished upon its approval.

What were the facts?

The assessee company initiated Corporate Insolvency Resolution Proceedings (CIRP) under the Insolvency and Bankruptcy Code. The Tribunal noted that the status of the CIRP was unknown and that the assessee did not appear for the hearing.

What were the issues?

Whether pending Income Tax appeals can continue when the assessee is undergoing Corporate Insolvency Resolution Proceedings and a moratorium is in effect.

Which sections of the Income-tax Act were involved?

Section 7,Section 13,Section 14,Section 31

AI-generated summary — verify with the full judgment below

Cases cited in this judgment(1)Show list

Detected automatically from the text. Citations are also linked where they appear in the judgment. The count shows how many other judgments on BharatTax rely on the same authority.

Income Tax Appellate Tribunal, HYDERABAD BENCHES “B”, HYDERABAD

Before: SHRI RAMA KANTA PANDA & SHRI K.NARASIMHA CHARY

For Respondent: Ms. M. Narmada, CIT-DR
Hearing: 15/09/2022

आदेश‍/ ORDER PER BENCH: Aggrieved by the order(s) passed by the learned Commissioner of Income Tax(Appeals)-4, Hyderabad (“Ld. CIT(A)”), in the case of Leo Meridian Infrastructure Projects & Hotels Limited (“the assessee”) for the assessment years 2007-08, 2008-09 & 2009-10 both the assessee and Revenue preferred these appeals.

2.

None appeared on behalf of the assessee. It is, however, seen from the record that the Corporate Insolvency Resolution Proceedings (CIRP) are initiated by admitting the application under section 7 of the Insolvency and Bankruptcy Code R/w Rule 4 of I&B (AAA) Rules, 2016 (“the Code”) by the National Company Law Appellate Tribunal (NCLAT) by order dated 09/04/2019. Learned DR submitted that the state of affairs obtaining as on today are not available and it is not known at what stage the CIRP are pending.

3.

Be that as it may, we have considered the issue in the light of the provisions of and the decision of the Hon'ble Apex Court in the case of Ghanashyam Mishra And Sons vs Edelweiss Asset Reconstruction (2021) 126 taxmann.com 132 (SC). Under section 13 of the Code, the adjudicating authority after admission of the application under section 7 or 9 or 10 of the Code shall declare a moratorium which shall include the prohibition of the institution of suits or continuation of pending suits or proceedings against the corporate debtor in any court of law or tribunal. In Ghanashyam Mishra And Sons (supra), it was held that, (i) That once a Leo Meridian Infrastructure Projects & Hotels Limited resolution plan is duly approved by the Adjudicating Authority under sub section (1) of Section 31, the claims as provided in the resolution plan shall stand frozen and will be binding on the Corporate Debtor and its employees, members, creditors, including the Central Government, any State Government or any local authority, guarantors and other stakeholders. On the date of approval of resolution plan by the Adjudicating Authority, all such claims, which are not a part of resolution plan, shall stand extinguished and no person will be entitled to initiate or continue any proceedings in respect to a claim, which is not part of the resolution plan; (ii) 2019 amendment to Section 31 of the I&B Code is clarificatory and declaratory in nature and therefore will be effective from the date on which I&B Code has come into effect; and (iii) Consequently all the dues including the statutory dues owed to the Central Government, any State Government or any local authority, if not part of the resolution plan, shall stand extinguished and no proceedings in respect of such dues for the period prior to the date on which the Adjudicating Authority grants its approval under Section 31 could be continued.

4.

A reading of the provisions under section 13 and 14 of the Code along with the decision in Ghanashyam Mishra And Sons (supra), clearly shows that once the proceedings have commenced by institution of application under section 7 or 9 or 10 of the Code, the continuance of the pending proceedings is prohibited and when once they reach the logical conclusion with due approval of the resolution plan by the Adjudicating Authority under sub section (1) of Section 31, the claims as provided in Leo Meridian Infrastructure Projects & Hotels Limited the resolution plan shall stand frozen and will be binding on the Corporate Debtor and its employees, members, creditors, including the Central Government, any State Government or any local authority, guarantors and other stakeholders.

5.

At any rate, for the time being, these appeals cannot be proceeded with during the continuance of the proceedings under the Code. Parties have to work out their remedies in the proceedings under the Code. However, depending upon the result of such proceedings before the adjudicating authority in respect of the corporate debtor, appropriate steps if any, may be taken by the appellant(s)/respondent(s). We, therefore, granting leave to the appellant(s)/respondent(s) in these appeals to seek the restoration of the appeals, if necessitated by the order in the Corporate Insolvency Resolution Proceedings, dismiss the appeals in limine. We derive support for the above proposition from the decision of the Mumbai Bench of the Tribunal in the case of Mahavir Roads & Infrastructure Pvt. Ltd., Vs. DCIT in to 651/Mum/2019 (AYs.2008-09 to 2013-14), dt.08/06/2022.

6.

In the result, all these appeals are dismissed in limine.