DY. COMMISSIONER OF INCOME TAX, CIRCLE-16(1), HYDERABAD vs. LANCO SOLAR PRIVATE LIMITED, HYDERABAD
In favour of the assessee: the Revenue's appeal was dismissed. From the AI summary of this appeal.
What did the Tribunal hold?
The Tribunal held that the continuance of pending proceedings against the corporate debtor is prohibited during the moratorium period. Parties are to work out their remedies before the Adjudicating Authority under the Code.
What were the facts?
Corporate Insolvency Resolution Proceedings (CIRP) were initiated against the assessee, leading to a moratorium under the Insolvency and Bankruptcy Code, 2016. The Tribunal was informed that the status of the CIRP was not available.
What were the issues?
Whether pending income tax appeals can continue during the moratorium declared under the Insolvency and Bankruptcy Code, 2016.
Which sections of the Income-tax Act were involved?
AI-generated summary — verify with the full judgment below
Cases cited in this judgment(1)Show listHide list
Detected automatically from the text. Citations are also linked where they appear in the judgment. The count shows how many other judgments on BharatTax rely on the same authority.
- Ghanashyam Mishra And Sons. v. Edelweiss Asset Reconstruction192 citing126 Taxmann.com 132 · 2021 · SC
Income Tax Appellate Tribunal, HYDERABAD BENCHES “A”, HYDERABAD
Before: SHRI INTURI RAMA RAO & SHRI K.NARASIMHA CHARY
आदेश / ORDER PER INTURI RAMA RAO, AM: Aggrieved by the orders passed by the learned Commissioner of Income Tax (Appeals)-4, Hyderabad [“Ld. CIT(A)” ] in the case of M/s. Lanco Solar Private Ltd., (“the assessee”), both the assessee and Revenue preferred these appeals. For the sake of convenience, we dispose of these appeals by this common order.
& 2219/Hyd/2018 2. At the outset it is represented by the Learned AR that the Corporate Insolvency Resolution Proceedings (CIRP) are initiated by admitting the application under section 7 of the Insolvency and Bankruptcy Code, 2016 (“the Code”) and moratorium under section 14 of the Code was declared by the National Company Law Appellate Tribunal (NCLAT) by order dated 17/05/2019. In terms of the moratorium, the institution and continuance of the proceedings against the assessee are prohibited. Learned DR submitted that the state of affairs obtaining as on today are not available and it is not known at what stage the CIRP are pending. Learned AR also submits that such facts are yet to be ascertained. There is no representation for the Corporate Insolvency Resolution Professional.
Be that as it may, we have considered the issue in the light of the provisions of and the decision of the Hon'ble Apex Court in the case of Ghanashyam Mishra And Sons vs Edelweiss Asset Reconstruction (2021) 126 taxmann.com 132 (SC). Under section 13 of the Code, the adjudicating authority after admission of the application under section 7 or 9 or 10 of the Code shall declare a moratorium which shall include the prohibition of the institution of suits or continuation of pending suits or proceedings against the corporate debtor in any court of law or tribunal. In Ghanashyam Mishra And Sons (supra), it was held that, (i) That once a resolution plan is duly approved by the Adjudicating Authority under sub section (1) of Section 31, the claims as provided in the resolution plan shall stand frozen and will be binding on the Corporate Debtor and its employees, members, creditors, including the Central Government, any State Government or any local authority, guarantors and other stakeholders. On the date of approval of resolution plan by the Adjudicating Authority, all such claims, which are not a part of resolution plan, shall stand extinguished and no person will be entitled to initiate or continue any proceedings in respect to a claim, which is not part of the resolution plan; (ii) 2019 amendment to Section 31 of the I&B Code is clarificatory and declaratory in nature and therefore will be effective from & 2219/Hyd/2018 the date on which I&B Code has come into effect; and (iii) Consequently all the dues including the statutory dues owed to the Central Government, any State Government or any local authority, if not part of the resolution plan, shall stand extinguished and no proceedings in respect of such dues for the period prior to the date on which the Adjudicating Authority grants its approval under Section 31 could be continued.
A reading of the provisions under section 13 and 14 of the Code along with the decision in Ghanashyam Mishra And Sons (supra), clearly shows that once the proceedings have commenced by institution of application under section 7 or 9 or 10 of the Code, the continuance of the pending proceedings is prohibited and when once they reach the logical conclusion with due approval of the resolution plan by the Adjudicating Authority under sub section (1) of Section 31, the claims as provided in the resolution plan shall stand frozen and will be binding on the Corporate Debtor and its employees, members, creditors, including the Central Government, any State Government or any local authority, guarantors and other stakeholders.
At any rate, for the time being, this appeal cannot be proceeded with during the continuance of the proceedings under the Code. Parties have to work out their remedies before the Adjudicating Authority under the Code. However, depending upon the result of such proceedings before the adjudicating authority in respect of the corporate debtor, appropriate steps if any, may be taken by the appellant/respondent. We, therefore, granting leave to the appellants/respondents in this appeal to seek the restoration of the appeal, if necessitated by the orders in the Corporate Insolvency Resolution Proceedings, dismiss the appeal in limine. We derive support for the above proposition from the decision of the Mumbai Bench of the Tribunal in the case of Mahavir Roads & Infrastructure Pvt. Ltd., Vs. DCIT in to 651/Mum/2019 (AYs.2008-09 to 2013-14), dt.08/06/2022. & 2219/Hyd/2018 6. In the result, both these appeals are dismissed in limine.
Order pronounced in the open court on this the 31st day of October, 2022.
More judgments on Section 7
- Reliance Home Finance Limited, Lower Parel… vs Pr. Commissioner of Income Tax-8…ITA 1759/MUM/2026[2017-18]Status: Disposed8 Sept 2026AY 2017-18
- Jaiprakash Associates Limited vs The Office of the Commissioner of Customs…W.P.(C)-10387/20262 Sept 2026
- DCIT, C-4(1), Chandigarh vs M/S Winsome Yarns Ltd, ChandigarhITA 886/CHANDI/2019[2015-16]Status: Disposed19 Mar 2026AY 2015-16
- M/S Winsome Yarns Ltd., Chandigarh vs ACIT, C-4(1), ChandigarhITA 571/CHANDI/2019[2015-16]Status: Disposed19 Mar 2026AY 2015-16
- ACIT, Chandigarh vs M/S Winsome Yarn Ltd., ChandigarhITA 31/CHANDI/2010[2006-07]Status: Disposed19 Mar 2026AY 2006-07
Recent GST High Court judgments
Search GST case law →- M/S Shivam Tiles House vs. State Of U.P. And AnotherAllahabad · 21 Oct 2026
- Imtiyaz Shaikh Z Chorlekar vs. Salman ShaikhBombay · 21 Oct 2026
- Dr Babasaheb Ambedkar Marathwada University Thr Its Registrar Prashant S Amrutkar vs. Union Of INDIA Thr The Secretary And OthersBombay · 19 Oct 2026
- Babasaheb Ambedkar Marathwada University Thr Registrar Prashant S Amrutkar vs. Union Of INDIA Thr Secretary And OthersBombay · 19 Oct 2026
- Vinishma Technologies Private Limited vs. State Of KarnatakaKarnataka · 17 Oct 2026