“percentage completion method”

ICDS & AccountingICDS IIIICDS III467 judgments

The decision most relied on for percentage completion method is CIT v. Bilahari Investment (P) Ltd. (299 ITR 1), cited in 206 judgments on BharatTax.

Leading authorities on percentage completion method

CIT v. Bilahari Investment (P) Ltd.
299 ITR 1 · 2008 · Supreme Court
206
citing judgments

The project completion method and the percentage of completion method are both recognized methods for recognizing income from real estate contracts.

CIT v. Hyundai Heavy Industries Co. Ltd.
291 ITR 482 · 2007 · Supreme Court
166
citing judgments

The Supreme Court held that the 'project completion method' and the 'percentage of completion method' are recognized accounting methods for ascertaining profit for contracts. The case affirms these methods in the context of contract accounts.

CIT v. ARUN EXCELLO FOUNDATIONS (P) LTD.
212 Taxmann 342 · 2013 · High Court
35
citing judgments

Accounting Standard 7 is not applicable to real estate developers, and therefore, the percentage of completion method cannot be imposed on them. Assessees are justified in following the project completion method as per Accounting Standard 9.

Prestige Estate Projects (P) Ltd. v. DCIT
33 DTR 514 · 2010 · ITAT
28
citing judgments

A real estate developer adopting the completed contract method of accounting cannot be forced to follow the percentage completion method under AS-7 if AS-7 has not been specified by the Central Government under section 145(2). The Assessing Officer cannot reject accounts under section 145(3) solely on this ground.

CIT v. Associated Cables P. Ltd.
286 ITR 596 · 2006 · High Court
25
citing judgments

Retention money withheld by a contractee is not taxable in the year it is retained, but only in the year the obligations under the contract are fulfilled and the amount becomes due to the assessee.

Mazagaon Dock Limited v. JCIT
29 SOT 356 · 2009 · ITAT
25
citing judgments

Anticipated or foreseeable losses on fixed-price construction contracts are deductible in the year the loss is foreseen, aligning with accounting standards like AS-7. This approach is supported by decisions allowing deduction of foreseeable losses based on technical estimation.

Wall Construction Co Ltd. v. JCIT
102 TTJ 505 · 2006 · ITAT
21
citing judgments

Interest expenditure on borrowed funds used for stock-in-trade is allowable as a deduction in the year the revenue is offered to tax, even when following the percentage completion method for recognizing revenue.

CIT v. Aditya Builders
378 ITR 75 · 2015 · High Court
21
citing judgments

The appropriate method of accounting to correctly reflect a true financial statement is a matter of opinion and debate, which is not amenable to revisional jurisdiction under Section 263 of the Act. The Assessing Officer cannot change the method of revenue recognition to the percentage completion method if the assessee has consistently followed the project completion method.

Judgments citing percentage completion method

DCIT, Coimbatore vs. M/S Rpp Infra Projects Limited, Erode

ITA 847/CHNY/2022[2016-2017]Status: DisposedITAT Chennai16 May 2025AY 2016-2017

Bench: Shri Manu Kumar Giri & Shri S.R.Raghunathaआयकर अपील सं./I.T.A.Nos.333, 334 & 335/Chny/2021 & Ita No.847/Chny/2022 (निर्धारण वर्ष / Assessment Years: 2012-13, 2013-14, 2017-18 & 2016-17) Deputy Commissioner Of Income Tax, Central Circle-2, Coimbatore. (अपीलार्थी/Appellant) Vs M/S. Rpp Infra Projects Limited, Sf No.454, Ragupathynaickenpalayam, Erode-638 002. Pan :Aaacr-9307-E (प्रत्यर्थी/Respondent) अपीलार्थी की ओर से / Appellant By प्रत्यर्थी की ओर से/Respondent By Mr. Shivanand K. Kalakeri, Cit Mr. N.Arjun Raj, Advocate सुनवाई की तारीख /Date Of Hearing घोषणा की तारीख / Date Of Pronouncement 25.02.2025 16.05.2025 आदेश / Order Per Bench: The Captioned Appeals Filed By The Revenue Are Directed Against Separate Orders Of The Ld. Ld. Commissioner Of Income Tax (Appeals)-18 / 19, Chennai [Cit(A)] Dated 24.02.2021 / 06.07.2022 For Assessment Years 2012-13, 2013-14, 2017-18 & 2016-17 Respectively. The Facts As Well As Issues Are Admittedly Identical In All These Years. For The Purpose Of Adjudication, Ay 2012-13 Has Been Taken To Be The Lead Year. 2. The Registry Has Noted Delay Of 127 Days In Filing Three Appeals For Ays 2012-13, 2013-14, 2017-18. Considering The Reasons Stated In The Affidavits By The Revenue, We Condone The Delay & Treat The Reasons As 'Sufficient Cause' & Admit These Appeals For Adjudication.

Section 250(1)Section 80Section 80I

assessee is eligible for deduction u/s.80IA of the Income tax Act, 1961 without taking into consideration that the assessee has earned profit on percentage completion method, thus earning income and claiming deduction even before the whole work is completed and also it is to be noted that the assessee ... eligible for deduction under section 801A(4). 9. It is further to be noticed that assessee is recognizing income from the projects on percentage completion method. Thus, even before the whole work of the project/infrastructure facility is completed assessee is recognizing income from the project and claiming deduction under section

Deputy Commissioner of Income Tax Central Circle-2, Coimbatore vs. M/S Rpp Infra Projects Limited, Erode

ITA 334/CHNY/2021[2013-14]Status: DisposedITAT Chennai16 May 2025AY 2013-14

Bench: Shri Manu Kumar Giri & Shri S.R.Raghunathaआयकर अपील सं./I.T.A.Nos.333, 334 & 335/Chny/2021 & Ita No.847/Chny/2022 (निर्धारण वर्ष / Assessment Years: 2012-13, 2013-14, 2017-18 & 2016-17) Deputy Commissioner Of Income Tax, Vs M/S. Rpp Infra Projects Central Circle-2, Coimbatore. (अपीलार्थी/Appellant) Limited, Sf No.454, Ragupathynaickenpalayam, Erode-638 002. Pan :Aaacr-9307-E (प्रत्यर्थी/Respondent) अपीलार्थीकीओरसे / Appellant By प्रत्यर्थीकीओरसे/Respondent By : Mr. Shivanand K. Kalakeri, Cit : Mr. N.Arjun Raj, Advocate सुनवाईकी तारीख/Date Of Hearing घोषणाकीतारीख / Date Of Pronouncement : 25.02.2025 : 16.05.2025 आदेश / Order Per Bench: The Captioned Appeals Filed By The Revenue Are Directed Against Separate Orders Of The Ld. Ld. Commissioner Of Income Tax (Appeals)-18 / 19, Chennai [Cit(A)] Dated 24.02.2021 / 06.07.2022 For Assessment Years 2012-13, 2013-14, 2017-18 & 2016-17 Respectively. The Facts As Well As Issues Are Admittedly Identical In All These Years. For The Purpose Of Adjudication, Ay 2012-13 Has Been Taken To Be The Lead Year. 2. The Registry Has Noted Delay Of 127 Days In Filing Three Appeals For Ays 2012-13, 2013-14, 2017-18. Considering The Reasons Stated In The Affidavits By The Revenue, We Condone The Delay & Treat The Reasons As 'Sufficient Cause' & Admit These Appeals For Adjudication.

For Respondent: Mr. Shivanand K. Kalakeri, CIT
Section 250(1)Section 80Section 80I

assessee is eligible for deduction u/s.80IA of the Income tax Act, 1961 without taking into consideration that the assessee has earned profit on percentage completion method, thus earning income and claiming deduction even before the whole work is completed and also it is to be noted that the assessee ... eligible for deduction under section 801A(4). 9. It is further to be noticed that assessee is recognizing income from the projects on percentage completion method. Thus, even before the whole work of the project/infrastructure facility is completed assessee is recognizing income from the project and claiming deduction under section

Shree Velu Builders Pvt. Ltd., Chennai vs. DCIT, Corporate Circle-3(1), Chennai

In the result, the appeal filed by the assessee is allowed for statistical purposes

ITA 560/CHNY/2025[2012-13]Status: DisposedITAT Chennai30 Apr 2025AY 2012-13

Bench: Shri S.S. Viswanethra Ravi & Shri Jagadishआयकर अपील सं./I.T.A. No.560/Chny/2025 िनधा"रण वष"/Assessment Year: 2012-13 Shri Velu Builders Private Limited, Vs. The Deputy Commissioner Of Block No. 2, Alaka Palazu, 4/219, Income Tax, Poonamallee High Road, Kattupakkam, Corporate Circle 3(1), Chennai 600 056. Chennai. [Pan:Aaacs6653C] (अपीलाथ"/Appellant) (""थ"/Respondent) अपीलाथ" की ओर से / Appellant By : Shri Girish Kumar, Advocate ""थ" की ओर से/Respondent By : Shri M.P. Guru Prasad, Addl. Cit सुनवाई की तारीख/ Date Of Hearing : 23.04.2025 घोषणा की तारीख /Date Of Pronouncement : 30.04.2025 आदेश /O R D E R Per S.S. Viswanethra Ravi: This Appeal Filed By The Assessee Is Directed Against The Order Dated 30.12.2024 Passed By The Ld. Commissioner Of Income Tax (Appeals), National Faceless Appeal Centre [Nfac], Delhi For The Assessment Year 2012-13. 2. The Assessee Raised 12 Grounds Of Appeal Amongst Which, The Only Issue Emanates For Our Consideration As To Whether The Ld. Cit(A) Is Justified In Confirming The Assessment Order Exparte Of The Assessee.

For Appellant: Shri Girish Kumar, AdvocateFor Respondent: Shri M.P. Guru Prasad, Addl. CIT
Section 142(1)Section 143(3)Section 144Section 148

noted that the assessee offered gross income at ₹.24,77,86,390/- being 56% of the advances received from the buyers based on percentage completion method of accounting and the expenditure was incorrectly claimed in respect of the income offered @ 56% of work completed. Accordingly, the Assessing Officer issued notice