“percentage completion method”

ICDS & AccountingICDS IIIICDS III467 judgments

The decision most relied on for percentage completion method is CIT v. Bilahari Investment (P) Ltd. (299 ITR 1), cited in 206 judgments on BharatTax.

Leading authorities on percentage completion method

CIT v. Bilahari Investment (P) Ltd.
299 ITR 1 · 2008 · Supreme Court
206
citing judgments

The project completion method and the percentage of completion method are both recognized methods for recognizing income from real estate contracts.

CIT v. Hyundai Heavy Industries Co. Ltd.
291 ITR 482 · 2007 · Supreme Court
166
citing judgments

The Supreme Court held that the 'project completion method' and the 'percentage of completion method' are recognized accounting methods for ascertaining profit for contracts. The case affirms these methods in the context of contract accounts.

CIT v. ARUN EXCELLO FOUNDATIONS (P) LTD.
212 Taxmann 342 · 2013 · High Court
35
citing judgments

Accounting Standard 7 is not applicable to real estate developers, and therefore, the percentage of completion method cannot be imposed on them. Assessees are justified in following the project completion method as per Accounting Standard 9.

Prestige Estate Projects (P) Ltd. v. DCIT
33 DTR 514 · 2010 · ITAT
28
citing judgments

A real estate developer adopting the completed contract method of accounting cannot be forced to follow the percentage completion method under AS-7 if AS-7 has not been specified by the Central Government under section 145(2). The Assessing Officer cannot reject accounts under section 145(3) solely on this ground.

CIT v. Associated Cables P. Ltd.
286 ITR 596 · 2006 · High Court
25
citing judgments

Retention money withheld by a contractee is not taxable in the year it is retained, but only in the year the obligations under the contract are fulfilled and the amount becomes due to the assessee.

Mazagaon Dock Limited v. JCIT
29 SOT 356 · 2009 · ITAT
25
citing judgments

Anticipated or foreseeable losses on fixed-price construction contracts are deductible in the year the loss is foreseen, aligning with accounting standards like AS-7. This approach is supported by decisions allowing deduction of foreseeable losses based on technical estimation.

Wall Construction Co Ltd. v. JCIT
102 TTJ 505 · 2006 · ITAT
21
citing judgments

Interest expenditure on borrowed funds used for stock-in-trade is allowable as a deduction in the year the revenue is offered to tax, even when following the percentage completion method for recognizing revenue.

CIT v. Aditya Builders
378 ITR 75 · 2015 · High Court
21
citing judgments

The appropriate method of accounting to correctly reflect a true financial statement is a matter of opinion and debate, which is not amenable to revisional jurisdiction under Section 263 of the Act. The Assessing Officer cannot change the method of revenue recognition to the percentage completion method if the assessee has consistently followed the project completion method.

Judgments citing percentage completion method

ACIT, Chennai vs. M/S. Bsr Builders Engineers Contractors, Chennai

In the result, the appeal of the assessee for AYs 2016-17 & 2017-18

ITA 1561/CHNY/2025[2016]Status: DisposedITAT Chennai14 Jan 2026

Bench: Shri Aby T. Varkey & Shri Jagadishआयकर अपील सं./Ita Nos.1311 & 1312/Chny/2025 िनधा"रणवष"/Assessment Years: 2016-17 & 2017-18 V. Bsr Builders Engineers Contractors, The Dcit, No.28, Bsr Janus, Tank Bund Road, Central Circle-2(3), Nungambakkam, Chennai-600 034. Chennai. [Pan: Aagfb 7140 N] (अपीलाथ"/Appellant) (""यथ"/Respondent) आयकर अपील सं./Ita Nos.1274 & 1561/Chny/2025 िनधा"रणवष"/Assessment Years: 2017-18 & 2016-17 V. The Dcit / Acit, Bsr Builders Engineers Central Circle-2(3), Contractors, Chennai. No.28, Bsr Janus, Tank Bund Road, Nungambakkam, Chennai-600 034. [Pan: Aagfb 7140 N] (अपीलाथ"/Appellant) (""यथ"/Respondent)

For Appellant: Mr.G. Baskar, Advocate &For Respondent: Mr.Nishanth Rao, JCIT

Rs.4,19,97,354/- by re-computing the income of the assessee from the real-estate project by applying the percentage completion method as against the plea of the assessee that it has been regularly following project completion method. The AO, in the course of assessment, noted that ... which was applicable in the relevant AY 2017-18, the assessee was statutorily required to disclose income from its projects under the percentage completion method, which it had not done so. In terms of the provisions of Section 43CB, the AO held that, as the assessee had completed more than

Bsr Builders Engineers Contractors, Chennai vs. DCIT, Central Circle-2(3), Chennai

In the result, the appeal of the assessee for AYs 2016-17 & 2017-18

ITA 1312/CHNY/2025[2017-18]Status: DisposedITAT Chennai14 Jan 2026AY 2017-18

Bench: Shri Aby T. Varkey & Shri Jagadishआयकर अपील सं./Ita Nos.1311 & 1312/Chny/2025 िनधा"रणवष"/Assessment Years: 2016-17 & 2017-18 V. Bsr Builders Engineers Contractors, The Dcit, No.28, Bsr Janus, Tank Bund Road, Central Circle-2(3), Nungambakkam, Chennai-600 034. Chennai. [Pan: Aagfb 7140 N] (अपीलाथ"/Appellant) (""यथ"/Respondent) आयकर अपील सं./Ita Nos.1274 & 1561/Chny/2025 िनधा"रणवष"/Assessment Years: 2017-18 & 2016-17 V. The Dcit / Acit, Bsr Builders Engineers Central Circle-2(3), Contractors, Chennai. No.28, Bsr Janus, Tank Bund Road, Nungambakkam, Chennai-600 034. [Pan: Aagfb 7140 N] (अपीलाथ"/Appellant) (""यथ"/Respondent)

For Appellant: Mr.G. Baskar, Advocate &For Respondent: Mr.Nishanth Rao, JCIT

Rs.4,19,97,354/- by re-computing the income of the assessee from the real-estate project by applying the percentage completion method as against the plea of the assessee that it has been regularly following project completion method. The AO, in the course of assessment, noted that ... which was applicable in the relevant AY 2017-18, the assessee was statutorily required to disclose income from its projects under the percentage completion method, which it had not done so. In terms of the provisions of Section 43CB, the AO held that, as the assessee had completed more than

Bsr Builders Engineers Contractors, Chennai vs. DCIT, Cent. Circle-2(3), Chennai

In the result, the appeal of the assessee for AYs 2016-17 & 2017-18

ITA 1311/CHNY/2025[2016-17]Status: DisposedITAT Chennai14 Jan 2026AY 2016-17

Bench: Shri Aby T. Varkey & Shri Jagadishआयकर अपील सं./Ita Nos.1311 & 1312/Chny/2025 िनधा"रणवष"/Assessment Years: 2016-17 & 2017-18 V. Bsr Builders Engineers Contractors, The Dcit, No.28, Bsr Janus, Tank Bund Road, Central Circle-2(3), Nungambakkam, Chennai-600 034. Chennai. [Pan: Aagfb 7140 N] (अपीलाथ"/Appellant) (""यथ"/Respondent) आयकर अपील सं./Ita Nos.1274 & 1561/Chny/2025 िनधा"रणवष"/Assessment Years: 2017-18 & 2016-17 V. The Dcit / Acit, Bsr Builders Engineers Central Circle-2(3), Contractors, Chennai. No.28, Bsr Janus, Tank Bund Road, Nungambakkam, Chennai-600 034. [Pan: Aagfb 7140 N] (अपीलाथ"/Appellant) (""यथ"/Respondent)

For Appellant: Mr.G. Baskar, Advocate &For Respondent: Mr.Nishanth Rao, JCIT

Rs.4,19,97,354/- by re-computing the income of the assessee from the real-estate project by applying the percentage completion method as against the plea of the assessee that it has been regularly following project completion method. The AO, in the course of assessment, noted that ... which was applicable in the relevant AY 2017-18, the assessee was statutorily required to disclose income from its projects under the percentage completion method, which it had not done so. In terms of the provisions of Section 43CB, the AO held that, as the assessee had completed more than

DCIT, Chennai vs. Bsr Builders Engineers Contractors, Chennai

In the result, the appeal of the assessee for AYs 2016-17 & 2017-18

ITA 1274/CHNY/2025[2017]Status: DisposedITAT Chennai14 Jan 2026

Bench: Shri Aby T. Varkey & Shri Jagadishआयकर अपील सं./Ita Nos.1311 & 1312/Chny/2025 िनधा"रणवष"/Assessment Years: 2016-17 & 2017-18 V. Bsr Builders Engineers Contractors, The Dcit, No.28, Bsr Janus, Tank Bund Road, Central Circle-2(3), Nungambakkam, Chennai-600 034. Chennai. [Pan: Aagfb 7140 N] (अपीलाथ"/Appellant) (""यथ"/Respondent) आयकर अपील सं./Ita Nos.1274 & 1561/Chny/2025 िनधा"रणवष"/Assessment Years: 2017-18 & 2016-17 V. The Dcit / Acit, Bsr Builders Engineers Central Circle-2(3), Contractors, Chennai. No.28, Bsr Janus, Tank Bund Road, Nungambakkam, Chennai-600 034. [Pan: Aagfb 7140 N] (अपीलाथ"/Appellant) (""यथ"/Respondent)

For Appellant: Mr.G. Baskar, Advocate &For Respondent: Mr.Nishanth Rao, JCIT

Rs.4,19,97,354/- by re-computing the income of the assessee from the real-estate project by applying the percentage completion method as against the plea of the assessee that it has been regularly following project completion method. The AO, in the course of assessment, noted that ... which was applicable in the relevant AY 2017-18, the assessee was statutorily required to disclose income from its projects under the percentage completion method, which it had not done so. In terms of the provisions of Section 43CB, the AO held that, as the assessee had completed more than