DCIT, GURGAON vs. M/S. ICI C&C JV, GURGAON

PDF · subscribers
ITA 1652/DEL/2016Status: DisposedITAT Delhi11 September 2019AY 2011-125 pages
AI SummaryRemanded

What did the Tribunal hold?

The Tribunal held that if the budgeted revenue was indeed reduced, the AO's addition would not be sustainable. The issue requires verification by the AO, and the assessee must provide evidence of the contract value reduction.

What were the facts?

The assessee, a joint venture, recognized revenue using the percentage of completion method. The Assessing Officer (AO) made an addition by recalculating revenue recognition based on AS-7, using a different budgeted revenue and actual cost incurred.

What were the issues?

The key issue is whether the budgeted revenue for the project was reduced, and if so, how this impacts the revenue recognition under the percentage of completion method.

Which sections of the Income-tax Act were involved?

None explicitly mentioned, but relates to revenue recognition principles for contracts.

AI-generated summary — verify with the full judgment below

Income Tax Appellate Tribunal, DELHI BENCH ‘D’ : NEW DELHI

Before: SHRI KULDIP SINGH & SHRI PRASHANT MAHARISHI

For Respondent: Smt. Naina Soin Kapil, Senior DR
Hearing: 26.08.2019

PER KULDIP SINGH, JUDICIAL MEMBER :

1.

Appellant, DCIT, Circle 1(1), Gurgaon (hereinafter referred to as the ‘Revenue’) by filing the present appeal sought to set aside the impugned order dated 25.01.2016 passed by the Commissioner of Income - tax (Appeals)-1, Gurgaon qua the assessment year 2011-12 on the grounds inter alia that :- “On the facts and circumstances of the case, Ld. CIT (A) has erred in deleting the addition of Rs.2,60,01,522/- made by the Assessing Officer by adopting Percentage of Completion Method (POCM) as per AS-7..”

2.

Briefly stated the facts necessary for adjudication of the issue at hand are : Assessee is a joint venture company engaged in installation and civil construction of transmission lines in the state of U.P. and work contract had been awarded to it by Isolux Ingeneria S.A.-MAN-JV who has received work contract from UP Power Transmission Company Ltd.. Assessing Officer (AO) made addition of Rs.2,60,01,522/- by applying AS – 7 whereas assessee has taken percentage of completion method based on percentage of total budgeted cost that was actually incurred by end of the given year. AO proceeded to conclude that the calculation of revenue recognition by percentage completion method, the budgeted revenue is taken as Rs.60,70,48,846/- and calculated revenue as per AS – 7 as under :-

Budgeted cost Rs.56,78,47959/- Cumulative Actual Cost Rs.6,72,53,820/- Cumulative Actual Cost Rs.6,72,53,820/- to be considered for AS- 7 %age completion Rs.6,72,53,820/- / 5,67,48,47,959 x 100 = 11.84% Revenue as per AS-7 11.84% of 60,70,48,846/- = Rs.7,18,96,629/-

3.

So, declining the contentions raised by the assessee that contract value has been reduced from Rs.82 crores to Rs.60 crores, AO taken the contract revenue as Rs.9,78,98,151/- instead of Rs.7,18,96,629/- taken by the assessee and made addition of Rs.2,60,01,522/-.

4.

Assessee carried the matter by way of an appeal before the ld. CIT (A) who has deleted the addition by allowing the appeal. Feeling aggrieved, the Revenue has come up before the Tribunal by way of filing the present appeal.

5.

Assessee has not preferred to put in appearance despite issuance of the notice and consequently, we proceeded to decide the present appeal with the assistance of the ld. DR as well as on the basis of documents available on the file.

6.

We have heard the ld. Departmental Representative for the revenue to the appeal, gone through the documents relied upon and orders passed by the revenue authorities below in the light of the facts and circumstances of the case.

7.

From the grounds raised by the Revenue, order passed by the lower Revenue authorities, arguments addressed and facts & circumstances of the case, the short question arises for determination in this case is :-

“as to whether budgeted revenue of the project has been reduced from Rs.82.68 crores to Rs.60.70 crores?

8.

Undisputedly, original value of the contract was Rs.82.68 crores.

Before AO, the assessee has not produced any evidence whatsoever to prove the fact that the original value of the contract was reduced from Rs.82.68 crores to Rs.60.70 crores. Perusal of the impugned order passed by the ld. CIT (A) does not disclose if evidence to prove this fact was brought on record who has rather proceeded to delete the addition on the ground that in such eventuality, “the AO has option to go with one set of figure i.e. either original budgeted revenue and original budgeted cost or revised budgeted revenue or revised budgeted cost and the AO was not justified in picking and choosing the original budgeted revenue and revised budgeted cost to apply AS-7.”

9.

However, we are convinced that in case the budgeted revenue of the project has been reduced from Rs.82.68 crores to Rs.60.70 crores then addition made by AO is not sustainable. In these circumstances, we are of the considered view that the issue is required to be verified by the AO and assessee shall produce the necessary evidence in this regard in the form of communication or some supplementary contract etc. In case, original budgeted revenue is verified to be reduced from Rs.82.68 crores to Rs.60.,70 crores then no addition is sustainable, otherwise assessment order passed by the AO shall prevail. Consequently, the appeal filed by the Revenue is allowed for statistical purposes. Order pronounced in open court on this 11th day of September, 2019.