DY. COMMISSIONER OF INCOME TAX, CIRCLE-16(1), HYDERABAD vs. LANCO INFRATECH LIMITED, HYDERABAD

PDF · subscribers
ITA 1113/HYD/2019Status: DisposedITAT Hyderabad19 September 2022AY 2011-125 pages

In favour of the assessee: the Revenue's appeal was dismissed. From the AI summary of this appeal.

AI SummaryDismissed

What did the Tribunal hold?

The Tribunal held that due to the moratorium under the Insolvency and Bankruptcy Code, the appeals cannot be proceeded with. The court referenced a Supreme Court decision stating that claims not part of a resolution plan stand extinguished.

What were the facts?

The assessee company, M/s. Lanco Infratech Limited, is undergoing Corporate Insolvency Resolution Proceedings (CIRP) under the Insolvency and Bankruptcy Code, 2016. A moratorium was declared, prohibiting the continuation of proceedings against the assessee.

What were the issues?

Whether pending income tax appeals can continue when the assessee is under moratorium due to insolvency proceedings. The impact of a moratorium under the Insolvency and Bankruptcy Code on ongoing legal proceedings.

Which sections of the Income-tax Act were involved?

Section 13,Section 14,Section 31

AI-generated summary — verify with the full judgment below

Cases cited in this judgment(1)Show list

Detected automatically from the text. Citations are also linked where they appear in the judgment. The count shows how many other judgments on BharatTax rely on the same authority.

Income Tax Appellate Tribunal, HYDERABAD BENCHES “A”, HYDERABAD

Before: SHRI RAMA KANTA PANDA & SHRI LALIET KUMAR

For Respondent: Shri Rajendra Kumar, CIT-DR
Hearing: 15/09/2022

आदेश / ORDER PER LALIET KUMAR, JM: Aggrieved by the order(s) dated 18/04/2019 passed by the learned Commissioner of Income Tax (Appeals)-4, Hyderabad (“Ld. CIT(A)”), in the case of M/s. Lanco Infratech Ltd., (“the assessee”) for the assessment year 2011-12, both the assessee and Revenue preferred these appeals. For the sake of convenience, we dispose-of these appeals by this common order.

2.

At the outset it is represented by the Learned AR that the Corporate Insolvency Resolution Proceedings (CIRP) are initiated by admitting the application under section 7 of the Insolvency and Bankruptcy Code, 2016 (“the Code”) and moratorium under section 14 of the Code was declared by the National Company Law Appellate Tribunal (NCLAT) by order dated 07/08/2017 and CIRP proceedings are pending. In terms of the moratorium, the institution and continuance of the proceedings against the assessee are prohibited. Learned DR submitted that the state of affairs obtaining as on today are not available and it is not known at what stage the CIRP are pending. Learned AR also submits that such facts are yet to be ascertained.

3.

Be that as it may, we have considered the issue in the light of the provisions of and the decision of the Hon'ble Apex Court in the case of Ghanashyam Mishra And Sons vs Edelweiss Asset Reconstruction (2021) 126 taxmann.com 132 (SC). Under section 13 of the Code, the adjudicating authority after admission of the application under section 7 or 9 or 10 of the Code shall declare a moratorium which shall include the prohibition of the institution of suits or continuation of pending suits or proceedings against the corporate debtor in any court of law or tribunal. In Ghanashyam Mishra And Sons (supra), it was held that, (i) That once a resolution plan is duly approved by the Adjudicating Authority under sub section (1) of Section 31, the claims as provided in the resolution plan shall stand frozen and will be binding on the Corporate Debtor and its employees, members, creditors, including the Central Government, any State Government or any local authority, guarantors and other stakeholders. On the date of approval of resolution plan by the Adjudicating Authority, all such claims, which are not a part of resolution plan, shall stand extinguished and no person will be entitled to initiate or continue any proceedings in respect to a claim, which is not part of the resolution plan; (ii) 2019 amendment to Section 31 of the I&B Code is clarificatory and declaratory in nature and therefore will be effective from the date on which I&B Code has come into effect; and (iii) Consequently all the dues including the statutory dues owed to the Central Government, any State Government or any local authority, if not part of the resolution plan, shall stand extinguished and no proceedings in respect of such dues for the period prior to the date on which the Adjudicating Authority grants its approval under Section 31 could be continued.

4.

A reading of the provisions under section 13 and 14 of the Code along with the decision in Ghanashyam Mishra And Sons (supra), clearly shows that once the proceedings have commenced by institution of application under section 7 or 9 or 10 of the Code, the continuance of the pending proceedings is prohibited and when once they reach the logical conclusion with due approval of the resolution plan by the Adjudicating Authority under sub section (1) of Section 31, the claims as provided in the resolution plan shall stand frozen and will be binding on the Corporate Debtor and its employees, members, creditors, including the Central Government, any State Government or any local authority, guarantors and other stakeholders. At any rate, for the time being, these appeals cannot be proceeded with during the continuance of the proceedings under the Code. However, depending upon the result of such proceedings before the adjudicating authority in respect of the corporate debtor, appropriate steps if any, may be taken by the appellant(s)/respondent(s). We, therefore, granting leave to the appellant(s)/respondent(s) in these appeals to seek the restoration of the appeals, if necessitated by the orders in the Corporate Insolvency Resolution Proceedings, dismiss the appeals in limine. We derive support for the above proposition from the decision of the Mumbai Bench of the Tribunal in the case of Mahavir Roads & Infrastructure Pvt. Ltd., Vs. DCIT in to 651/Mum/2019 (AYs.2008-09 to 2013-14), dt.08/06/2022.

5.

In the result, both the appeals are dismissed in limine.

Order pronounced in the open court on this the 19th day of September, 2022.