No AI summary yet for this case.
Income Tax Appellate Tribunal, DELHI BENCH ‘G’ NEW DELHI
Before: SHRI G.D. AGRAWAL & SHRI SUDHANSHU SRIVASTAVA
PER SUDHANSHU SRIVASTAVA, JUDICIAL MEMBER ITA 1950/12 has been preferred by the Department against
the order dated 20.01.2012 passed by the ld. CIT(Appeals)-XXVII, New
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09
Delhi for A.Y. 2008-09. CO 20/2015 has been preferred by the
assessee against the Departmental Appeal. ITA 5614/12 has been
preferred by the Department against the order dated 27.08.2012
passed by the ld. CIT(Appeals)-XXVII, New Delhi for AY 2009-10. ITA
5849/12 is the cross appeal by the assessee for AY 2009-10. As the
three appeals and the CO were heard together, they are being
disposed of by this common order.
ITA 1950/2012 & CO 20/2015
Return declaring an income of Rs. 11,00,06,440/- was filed on
29.09.2008. In the assessment order passed u/s 143(3) of the Income
Tax Act, 1961 (hereinafter called ‘the Act’), the AO determined the
income of the assessee at Rs. 36,88,00,000/- after making an addition
of Rs. 25,91,00,000/- by rejecting the project completion method of
accounting followed by the assessee. The assessee is a partnership
firm having two partners namely M/s Shipra Estate Ltd. (50% share)
and M/s Jai Kishan Estate Developers (P) Ltd. (50% share). The
assessee firm entered into joint venture with Ghaziabad Development
Authority (GDA) for the construction and development of housing
projects on two plots of land bearing plot no. 14 and plot no. 15
situated in Indirapuram at Ghaziabad. The firm had commenced
development of ‘Vista’ project in the year 2005 and ‘Shristi’ project in
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09
the year 2007 on the two plots respectively as mentioned above.
During the year, the assessee had carried on the work on both the
projects. The method of accounting being followed by the assessee
was Project Completion Method and the revenue was recognized at the
time of registration of the residential unit in the name of the
customer. Till the completion of the project, amounts received from
the customers against the booking of the flats were shown as
advances and were reflected as liabilities in the Balance Sheet. The
expenses incurred were shown under work-in-progress. The AO
noticed that as on 31.03.2008, the assessee had received a total
amount of Rs. 228.25 crores from the customers in respect of the
Vista project. The total estimated cost of the project was Rs. 209.81
crores. As per the allotment letters, the total sales price of the Vista
flats was calculated by the AO at Rs. 250.24 crores. The assessee had
already received an amount of Rs. 228.25 crores (91.21% of the total
sale price of the flats). The AO opined that receipt of 91.21% showed
that the flats were in advanced stage of completion and that the Vista
project had been substantially completed. It was the AO’s observation
that the income had not only accrued but had in effect been received
by the assessee. The AO further opined that the method of
accounting being followed by the assessee was so arranged with a
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09
view to distort the profits. The AO also observed that in a letter to the
bank, the assessee had stated the completion date of Vista Project as
2007 itself. Thus, based on all these observations, the AO rejected the
method of accounting i.e. Project Completion Method followed by the
assessee.
On appeal, the ld. First Appellate Authority allowed the
assessee’s appeal by holding that Project Completion Method was a
recognized method of accounting prescribed by the Institute of
Chartered Accountants of India (ICAI) and had been regularly followed
by the assessee. The ld. CIT (A) observed that since the assessee was
a real estate developer and not a construction contractor, Project
Completion Method was the right method for determining the profits
of the assessee. The addition of Rs. 25,91,00,000/- made by the AO
was deleted.
Now the Department is in appeal before us and has challenged
this deletion. In the CO, the assessee has challenged the rejection of
assessee’s claim for allowance of deduction u/s 80IB (10) of the Act by
the ld. CIT (A).
The ld. DR submitted that the AO had rejected the method
of accounting after a very thoughtful deliberation. He submitted
that careful consideration of the accounts of the assessee show
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09
that the assessee has followed neither the cash system nor the
accrual system of accounting and that the profits that have been
offered for taxation is a distorted figure for avoiding the
assessee's tax liability. It is seen that the assessee has received
Rs.373.17 crores as advances from its customers. It is worth
emphasizing that income has not only accrued but has also been
received by the assessee .There is nothing to show that there is
any uncertainty with regards to the ultimate receipts of the
revenues since these payments have already been received by the
assessee. A careful perusal of the chart of advances received from
the customers shows that in most of the cases in which
allotment has been made the payments have already been
received. It is seen that in the Vista project the total Sales price
of all the flats, as per the allotment letters issued to customers is
Rs 250.24 crores. As against this Rs 228.25 crores have already
been received as on 31.03.2008. Thus it is seen that 91.21% of
the selling price has already been received by the assessee. It was
also submitted that barring a few cases, 100% payments have
been received for each flat. These facts go on to show that the
Vista project has been substantially completed. It would be
appreciated that as per the conditions laid down in the allotment
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09
letter the consideration from the customers is to be received in
instalments. The customers are required to pay certain amount
at the time of application and the balance in seven equal
instalments at the interval of 3 months. As is the normal practice
in the case of real estate builders, instalments are linked to
stages of construction and completion of the flats. More than
91% of the total sales consideration could not have been received
unless all the flats were in an advanced stage of completion.
Moreover the assessee had submitted to the bank a letter for
sanction of finance where it had estimated that the Vista Project
would be completed in 2007 itself. The Ld DR drew our attention
to the Balance Sheet and submitted that that the assessee has
shown huge amounts as work-in-progress. The consolidated
estimated cost of Vista plus Srishti was Rs 536.08 crores. The
inventory shown in the balance sheet together with the expenses
that have been shown in the Profit & Loss a/c work out to more
than Rs 220 crores, which is a substantial proportion of the
estimated cost. It must be kept in mind that this is the
consolidated cost of both the projects and the Proportion of cost
incurred with respect to Vista is much higher. Thus it emerges
that a very high proportion of estimated cost of Vista has already
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09
been incurred by the assessee. Therefore even from the cost
incurred point of view there is no doubt that a major portion of
the project has been completed.
The Ld. DR submitted that in light of the observations of the
AO, the correct method of accounting is Percentage Completion
Method and, therefore, impugned order should be set aside.
The ld. AR submitted that the assessee is a Real Estate
Developer and not a contractor or an investor. It was submitted that
real estate development, or property development, is a multifaceted
business process, encompassing activities that range from the
renovation and re-lease of existing buildings to the purchase of raw
land and the sale of developed land or parcels to others. Real estate
developers are the people and companies who coordinate all of these
activities, converting ideas from paper to real property. Real estate
development is different from construction, although many developers
also manage the construction process. The Ld. AR submitted that
Developers buy land, finance real estate deals, build or have builders
build projects, create, imagine, control and orchestrate the process of
development from the beginning to end. Developers usually take the
greatest risk in the creation or renovation of real estate—and receive
the greatest rewards. Typically, developers purchase a tract of land,
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09
determine the marketing of the property, develop the building program
and design, obtain the necessary public approval and financing, build
the structures, and rent out, manage, and ultimately sell it.
Sometimes property developers will only undertake part of the
process. For example, some developers source a property; get the
plans and permits approved before on selling the property with the
plans and permits to a builder at a premium price. Alternatively, a
developer that is also a builder may purchase a property with the
plans and permits in place so that they do not have the risk of failing
to obtain planning approval and can start construction on the
development immediately. Developers work with many different
counterparts along each step of this process, including architects, city
planners, engineers, surveyors, inspectors, contractors, leasing agents
and more. The Ld. AR submitted that the modus operandi of the
assessee was as under:
Joint Venture with Ghaziabad Development Authority (i)
(GDA). GDA contributes land and continues to be its owner.
Assessee undertakes approval, construction, development, (ii)
completion, marketing and sale of project.
Assessee appoints contractor for construction purposes. (iii)
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09
The assessee as per the terms and conditions of Flat (iv)
Buyer’s agreement recognizes the transaction only when the flat
is delivered to the customer and is registered in the customer’s
name by Ghaziabad Development Authority.
Till the flat is registered, the buyer cannot sell the same and (v)
exit.
The assessee accounts for income / sale only when it (vi)
registers the flats in the name of the customers and till then the
amount received is treated as advance and shown as a liability in
the Balance Sheet and the expenditure incurred is treated as
work in progress.
The Ld. AR further submitted that the ICAI has clarified that
Revised Accounting Standard 7 – ‘Construction Contract’ is
applicable to only contractors and not to builders and real estate
developers. AS-9 Revenue Recognition is applicable to Real
Estate Developers. AS 9 recognizes both proportionate
completion method and the completed service contract method
for revenue recognition. A real estate developer can choose the
project completion method for revenue recognition. He pointed
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09
out that there is no dispute on the correctness and accuracy of
the accounts maintained by the assessee and that the aforesaid
method has been consistently applied and followed by the
assessee. The ld. Assessing Officer has changed the method for
the first time in Assessment Year 2008-09. He submitted that
any change in the method will result in the income from
Assessment Year 2006-07 to Assessment Year 2012-13 to be
recomputed which would be contrary to the judgment of the
Hon'ble Supreme Court in the case of Excel Industries Ltd. 358
ITR 295 wherein it has been held that an exercise which only
results in change in income in various years but is overall tax
neutral need not be pursued. Here also, the method suggested
by the Assessing Officer will only result into profit for each year
being different but the overall profitability will be the same. He
relied on the judgment of the Hon'ble Supreme Court in M/s
Bilahari Investment (2008) 299 ITR 1 for the preposition that
every assessee is entitled to arrange its affairs and follow the
method of accounting, which the Department has earlier
accepted. It is only in those cases where the Department records
a finding that the method adopted by the assessee results in
distortion of profits, the Department can insist on substitution of
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09
the existing method.
On the ground raised in the CO by the assessee on the issue of
deduction u/s 80-IB (10) of the Act, the ld. AR submitted that this
ground was taken before the ld. CIT (A) as Ground no. 4. However,
the ld. CIT(A) rejected the ground in para 22 of the impugned order by
observing that since the method of accounting being regularly followed
by the assessee has been accepted, this ground is rejected as having
become in fructuous. It was submitted that this ground was not an
alternate ground but on additional claim to which the assessee was
entitled.
We have heard the rival submissions and perused the material
on record. The following facts remain uncontroverted:
During the year under consideration, the assessee was
developing two Projects namely Vista and Sristhi in joint venture with
Ghaziabad Development Authority. The Vista project was started in
the year 2005 and had made considerable progress by the end the
Financial Year. The assessee was following Project Completion Method
of accounting and the revenue was recognized at the time of
registration of the residential unit in the name of the customer. Till
the time of registration of the residential units the amounts received
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09
from the customers were being treated as advances and were reflected
in the Balance Sheet as Liabilities. The cost associated with the
development and construction of the residential units was being
shown under the head ‘work-in-progress’. Registration in the name of
the customers was done by the Ghaziabad Development Authority
who continued to be owner of the Project and the assessee was
granted only development rights. The primary reason why the A.O.
rejected the Project Completion Method and has applied the
Percentage Completion Method is that the assessee had received
substantial portion of the total sale consideration of the residential
units in the Vita Project i.e. 91.21%. This amount was being shown by
in the balance sheet under the head liabilities and was not reflected in
the Profit & Loss account. The fact that 91% of the total sale price had
been received led to the inference that the Vista Project was
substantially complete as on 31.3.2008. AO, therefore, treated the
advances of Rs.228.25 Crores as sale consideration in respect of the
various residential units in Vista Project. The A.O. then worked out
the proportionate cost of development and construction of the Project
by multiplying the total cost of the Project with 91.21%. The difference
of the two was treated as profits of the assessee.
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09
In this regard it is seen that Project Completion Method
followed by the assessee is a recognized method of accounting
prescribed by the Institute of Chartered Accountant of India.
Before its revision in 2002, AS-7 was applicable in the case of
both the Construction Contractors and Real Estates Builders
and Developers. AS-7 prescribed both the Percentage
Completion Method and the Project Completion Method and it
was the choice of the assessee to follow either one of the
methods. The ICAI has clarified that the revised AS-7 is
applicable only in the case of Construction Contractors and in
the case of Real Estates Builders and Developers AS-9 is
applicable which prescribes Project Completion Method of
accounting. It is established legal position that an assessee can
follow any recognised method of accounting and the condition is
that the same method has to be followed consistently. In case of
a building project, the Institute of Chartered Accountants of
India which is an authority on prescribing accounting
standards had prescribed accounting standard AS-7 in 1983 for
accounting of income in respect of real estate projects and in
terms of AS-7 which was applicable to both contractor and real
estate developer, a person is free to follow either of project
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09
completion method or percentage completion method depending
upon the nature of project. The assessee, in this case, has
followed project completion method which is one of the
prescribed methods by the Institute of Chartered Accountants
of India. Even in terms of the revised accounting standard
which was applicable for most part of the work done by the
assessee the income had been correctly declared as per project
completion method in the year of completion. The assessee has
followed project completion method which was one of the
prescribed methods and the same method has been accepted by
the department in the earlier years. Department, therefore,
cannot reject the method and apply percentage completion
method in a subsequent year.
In view of discussion of the facts of the case and the legal
position as above it is held that the Project Completion Method
followed by the appellant is a recognized method of accounting
prescribed by the ICAI which has been regularly followed by the
assessee. The assessee being a real estate developer and not a
construction contractor, Project Completion Method is the right
method for determining the profits. The Project Completion
Method being followed should not have been disturbed by the
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09
Assessing Officer as it was being regularly followed by the
assessee in earlier years also and there is no cogent reason to
change the method. We, accordingly, uphold the findings of the
Ld. CIT(A) on this issue.
Hence, ground no. 1 of Department’s appeal is rejected. Accordingly, the appeal of the Department is rejected. 15. As far as the CO of the assessee is concerned, we are in
agreement with the submission of the ld. AR that the assessee’s claim
u/s 80-IB (10) of the Act was not an alternate claim to the assessee’s
method of accounting having been rejected. It was an additional
claim which somehow has been misconstrued by the ld. CIT (A) and
we deem it fit to restore this limited issue of claim u/s 80-IB (10) of
the Act to the file of the ld. CIT (A) to examine it afresh in light of the
existing legal requirements and fulfillment thereof by the assessee
after providing due opportunity to the assessee for presenting its case.
In the result, the CO of the assessee is allowed for statistical purposes. ITA 5614/2012 & ITA 5849/2012 17. Return showing income of Rs. 24,14,37,960/- was filed on
25.03.2010. In the assessment order passed u/s 143(3) of the Act,
the income was determined at Rs. 60,91,00,000/- after making an
addition of Rs. 36.77 crores. Out of this addition, disallowance u/s
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09
80IB(10) was to the extent of Rs. 29.68 crores and the balance
amount of Rs. 7.09 crores was added on account of application of
Percentage of Completion Method by the AO in place of Project
Completion Method followed by the assessee. As in the preceding
assessment year, the assessee was engaged in the business of Real
Estate Development and the assessee firm had entered into a Joint
Venture with Ghaziabad Development Authority (GDA) for
development of housing projects on two parcels of land bearing Plot
No. 14 and 15 situated in Indirapuram at Ghaziabad and had entered
into a Memorandum of Understanding (MOU) with GDA on
08.01.2001. As per the MOU, GDA was to continue to be owner of the
property and the assessee firm, after undertaking the construction,
development and completion of the projects was to market the same.
The conveyance deed with the buyers of the flats was to be executed
by the GDA. During the year under consideration, the assessee had
shown sales of Rs. 154.94 crores in respect of flats sold in the ‘Vista’
Project and the profit was shown at 53.82 crores. The assessee had
been regularly following the Project Completion Method and the
accrual system of accounting. The revenue was recognized by the
assessee at the time of registration of the property by GDA in the
buyer’s name. Till the time of registration of the residential units, the
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09
amounts received from the customers were being treated as advances
and were reflected in the Balance Sheet as liabilities. The cost
associated with the development and construction of the residential
units was being shown as work-in-progress. The AO, proceeding on
the same reasoning as in the preceding AY i.e. AY 2008-09, was of the
opinion that the assessee should have followed the percentage of
Completion Method for showing its correct taxable profits during the
year under consideration. As per the AO, the estimated Sale Value of
the Vista Project was Rs. 351.58 crores against which the assessee
had already received an amount of Rs. 295.43 crores which was about
84% of the total estimated sales. Therefore, as per the AO, the income
had not only accrued but had also been received by the assessee.
Thereafter, the AO proceeded to apply Percentage of Completion
Method and made on addition of Rs. 36.77 crores on this count. The
ld. CIT (A) deleted this addition is entirety following his earlier year’s
order in AY 2008-09.
Apart from this, out of the profits of Rs. 53.82 crores shown by
the assessee on sales finalized during the year under consideration,
an amount of Rs. 29.68 crores was claimed as deduction u/s 80IB(10)
of the Act in respect of the ‘Vista’ Project. The Vista Project was
divided into five sub projects as under:
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09
i. Vista A&B Blocks having 2 Towers and 320 flats.
ii. Vista D&E Blocks having 2 Towers and 320 flats.
iii. Vista B1, B2 & B3 Blocks having 3 Towers and 120 flats also
called C Block.
iv. Vista B4, B5, B6 & B7 Blocks having 4 Towers and 144 flats
also called F Block.
v. Vista Commercial Block having 80 shops.
The assessee had claimed deduction u/s 80IB (10) in respect of
two bed room flats in Block A,B, D and E in respect of 346 flats sold
during the year (out of 640 total flats sold). The project was approved
on 02.06.2005 and the completion certificate was dated 14.01.2010.
The total plot area of the project was 5.33 hectares or 13 acres
approximately. The AO disallowed deduction u/s 80IB(10) on the
ground that the area of the residential units on which the deduction
was claimed was more than 1000 sq. fee each as the area mentioned
in the sale deed was 99.96 sq. mts. Or 1067.74 sq. feet and hence the
conditions of section 80IB (10) (c) were not fulfilled. The other
objection of the AO to the claim was that the shop and commercial
establishment included in the Vista Housing Project exceeded the
limit prescribed in clause (d) of section 80IB(10) i.e. 5% of the
aggregate built up area of the housing project or 2000 sq. feet
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09
whichever is less. As per the AO, the total built up area of the
commercial establishment was 4896.2 sq. mts. or 52702 sq. feet. The
third point of the AO’s objection was that the Audit Report in Form
10CCB as per Rule 18BBB of the Income Tax Rules, 1962 had not
been filed separately by the assessee in respect of Vista A&B and Vista
D&E and also that the Profit/Loss Accounts and Balance Sheets of
these two Towers had not been audited separately and hence it was
difficult to rely on the claim of deduction u/s 80IB. The entire claim
of deductions amounting to Rs. 29.68 crores was denied by the AO.
Subsequent to the disallowance of deduction, the AO referred
the matter of determining the area of each flat to the DVO. The DVO
submitted his report specifying the area of the flats as under:
S. Floor Type of Flat No. of Flats Area of Total area (in Sq. No. Ft.) in A,B,C & Built up Balcony D Blocks (open to Area of Flat Sky) in sq. i/c Walls & ft.) covered Balcony (in sq.ft.) Comer 1029.28 231.28 1260.56 1st 1. 16 1st 2. 16 988.79 118.05 1106.84 Middle (Porch Side) 3. Middle 32 988.79 255.96 1244.75 1st 4. Comer 144 1029.28 Nil 1029.28 2nd to 10th 5. Middle 432 988.79 Nil 988.79 2nd to 10th
20.1 Thus, the DVO held that only 432 flats i.e. the middle flats on
2nd & 10th floor of Blocks A,B,D&E were having built up area of less
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09
than 1000 sq. feet and hence qualifying for deduction u/s 80IB(10) of
the Act. The remaining flats were held to have built up area of more
1000 sq. feet and not eligible for deduction.
Aggrieved, the assessee filed an appeal before the First
Appellate Authority and objected to certain observations of the DVO
with regard to the working of the built up area of the various flats. It
was submitted that with respect to 16 porch size Middle Flats and 32
Middle Flats on 1st Floor, the DVO had included the area of a balcony
which was open to the sky in the built-up area which should not have
been included in calculation of the built up area in terms of definition
of the built up area provided in the Act. The assessee’s plea before the
ld. CIT (A) was that this inclusion had resulted in the built up area of
these flats crossing 1000 sq. feet. The assessee also objected to the
working of the DVO in respect of the built up area of 144 corner flats
on floor nos. 2 and 10 on all the four blocks. The assessee also
submitted before the ld. CIT(A) that admittedly as some of the flats in
respect of which deduction u/s 80IB(10) had been claimed had built
up area exceeding 1000 sq. feet the deduction should be allowed in
respect of flats having built up area of less than 1000 sq. feet on a
proportionate basis.
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09
As far as the issue of the area of shops/commercial
establishment was concerned, the assessee submitted before the First
Appellate Authority that commercial establishment was a separate
sub-project within the overall Vista Project. Although the AO had
treated it as an integral part of the Vista Project, Vista Project had five
separate and independent sub-projects viz. Vista A&B, Vista D&E and
Vista C. Vista D comprised of only residential units in form of
separate towers and commercial establishment was having separate
entry and exit which had also been independently certified specifically
by the DVO in his report. It was the assessee’s submissions before
the ld. CIT(A) that the commercial establishment was not included in
the housing project and, therefore, clause (d) of section 80IB(10) was
not violated. It was further emphasized that no profits from the sale
of commercial space was claimed as deduction u/s 80IB and only the
profits resulting from the sale of residential units was claimed as
deduction. It was also submitted before the ld. CIT(A) that if the AO’s
view of the commercial establishment being included in the Vista
Housing Project were to be held as correct, then the profits from the
sale of commercial space would become an allowable deduction u/s
80IB(10) in AY 2010-11 as the provisions of the Act had been
amended w.e.f. 1.4.2010 according to which a project approved after
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09
1.4.2005 could be completed in five years from the end of the
Financial Year in which the approval was obtained (Assessee’s Project
approved on 2.6.2005 and completed by 31.3.2011). The assessee
also relied on the decision of ITAT, Delhi in its own case in ITA Nos.
2613, 2614, 2739 & 2741 in which it was held that when the total
shopping area was below 5% of the total area and the project was
approved and in conformity with GDA approval, then deduction u/s
80IB had to be allowed for the whole project. Regarding the AO’s
observation on the Audit Report, the assessee submitted before the ld.
CIT (A) that separate books of account had been maintained for each
of the sub-projects but the auditors had provided their opinion on the
consolidated accounts. Since the Report in Form 10CCB confirmed to
the guidelines issued by the ICAI, the same should not have been
ignored.
The ld. CIT (A) after considering the assessee’s submissions
decided the issues as under:
i. The assessee’s contention that deduction u/s 80IB (10) in
respect of flats having built-up area of less than 1000 sq. feet
should be allowed on a proportionate basis was accepted. 232
flats were held eligible for deduction out of 346 flats sold as per
the DVO’s report and the extent of allowable deduction was
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09
worked out at 19.28 crores. The issue was restored to the file of
AO for verifying the calculation and allowing the claim in respect
of 232 flats.
ii. The assessee’s contention that the flats having balcony open to
sky and included in the built up area of the flats by the DVO
should also qualify for deduction was however rejected.
iii. The assessee’s contention that the Vista Project comprised of five
separate sub-projects with the shopping area having its own
separate entry and exit was also accepted and it was held that
the built up area of the shopping commercial establishment is to
be taken into account only when such commercial establishment
is included in the housing project in terms of section 80IB (10(d).
iv. The ld. CIT(A) also accepted assessee’s contention that no defects
were pointed out by the AO with respect to the accounts and,
therefore, the deduction u/s 80IB(10) could not be disallowed on
the ground that the auditors had given their opinion on the
consolidated accounts of the assessee.
Now both the assessee, as well as the Department, is in appeal
before us.
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09
ITA No. 5614 has been filed by the Department and the
grounds of appeal are as under:
"On the facts and in the circumstances of the case, the Ld. CIT(A) had erred in deleting the addition of Rs 7.09 crores made by made by the A.O, under percentage completion method, when the assessed has already received 84% of the selling price of the flat and shown as advance from the customer
2 “On the facts and in the circumstances of the case, the Ld, CIT(A) has erred in allowing deduction u/s 80IB (10) amounting to Rs.10.40 crores on proportionate basis as against Rs.29 68 crores claimed by the assessee when the assesses did not fulfill all the conditions specified in the said section'
"On the facts and in the circumstances of the case, the Ld. 3 CIT (A) has erred in not considering the fact that No separate approval was taken from Ghaziabad Development authority (GDA in short) for the project named Vista (Blocks A & B; D&E) on which deduction u/s 80 IB (10) claimed and the map approved by GDA was for the entire project named Vista at Plot No. 14, Indirapuram, Ghaziabad (UP)." "On the facts and in the circumstances of the case, the Ld 4 CIT (A) order deserves to be cancelled and the assessment order needs to be confirmed.”
ITA 5849 is the assessee’s appeal and the grounds of appeal are
as under:
That the project of the appellant company fulfills all the 1. requirements of section 80IB (10) of the Act and as such, appellant company is entitled to the benefit of exemption under section 80IB (10) of the Act as claimed. The assessing officer went wrong on facts and in law in disallowing the claim of deduction of Rs. 29.68 crore under section 80IB (10) of the Act and consequently the Commissioner of Income Tax,
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09
(Appeal)-XXVII, New Delhi in principle allowed the deduction under section 80IB (10) of the Act but erred on facts and in law to restrict the deduction to Rs. 19.28 crores calculated for 232 flat out of the total deduction of Rs. 29.68 crores claimed on 346 flats. The observation made and bases adopted are unjustified and bad in law. The deduction under section 80IB (10) to have been allowed at Rs. 29.68 crore as claimed. The order passed by the Hon’ble CIT (Appeal), may kindly be modified accordingly.
That the DVO on reference from the AO submitted report to the AO wherein the area of 114 flat has been held to be more than 1000 sq.ft by including the area of the balcony which is open to sky. The CIT(Appeal)-XXVII, New Delhi thus erred on facts and in law in adopting the report of the DVO and restricting the deduction under section 80IB(10) of the Act and in doing so he ignored the facts and circumstances of the case and thus the deduction restricted is illegal and unjustified and bad in law.
On ground no. 1 of the Department’s appeal, the ld. AR
submitted that the ground is the same as in earlier year i.e. AY 2008-
09 which has already been argued before us. We concur with the
submissions of the ld. AR and in view of our findings in ITA
1950/Del/2012 on this issue; we dismiss ground no. 1 of the
Department’s appeal.
Ground Nos. 2 & 3 of the Department’s appeal and ground
nos. 1 & 2 of the assessee’s appeal are being taken up together as
they all relate to the claim of deduction u/s 80IB(10) of the Act. As
per the Department, the claim u/s 80IB(10) was not allowable as no
separate approval for the four projects viz. Vista A, B, D & E was
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09
taken and only a consolidated approval for the entire Vista Project was
taken from the GDA containing seven projects (Vista A to F and one
Commercial). It was the observation of the AO that the whole Vista
Project on plot no. 14 was approved by the GDA as one project. The
ld. DR submitted that as the housing project and the commercial
project were approved on the same map, the commercial project would
have to be included in the housing project. The ld. AR submitted that
projects A&B and D&E were two housing projects where the flats were
less than 1000 sq. ft. each. Each of these two housing projects did
not have any commercial establishment and comprised of only
residential units. It was submitted that separate books of account,
profit/loss account were prepared for the commercial project as well
as for each of the residential projects. It was the plea of the ld. AR
that commercial project has been treated as a separate independent
activity on which no deduction u/s 80IB (10) was ever claimed by the
assessee. The ld. AR also referred to the Report of the DVO, wherein
the DVO himself has admitted that the entrances and exits of the
Vista Shopping Complex and Vista Residential Project were separate
and not interconnected. It was submitted that the entire project
comprised of six residential projects and one commercial project and
no deduction had ever been claimed in respect of projects C, F and the
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09
Commercial Project and, therefore, there was no valid reason for
denial of deduction for Projects A & B and D & E which contained
each unit measuring less than 1000 sq. ft. The ld. AR reiterated that
the commercial project was completely different, separate and distinct
from each of the six residential projects and that there was no
commercial office space or area in any of the housing projects in A &
B and D & E.
As far as the issues of exclusion of projections that were open
to sky and that of incorrect measurements by the DVO were
concerned, the ld. AR submitted a chart depicting the built-up area of
the various flats as per the DVO report. The same is being
reproduced herein under for a ready reference:
S.No. Floor Remarks Type of flat No. of flats in Built up area Area of Total area (in of flat i/c Balcony sq. ft.) walls & (Open to A.B.D.E covered Sky) (in balcony (in sq.ft.) sq. ft.) projects
1st Corner 231.28 1260.56 1029.28 Details as per 1. 16 Annexure 'A'
2 1st 16 988.79 118.05 1106.84 Middle(Por Details as per ch side) Annexure ‘B’
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09
1st 32 988.79 255.96 1244.75 Middle Details as per Annexure 'C'
Corner 144 1029.28 Nil 1029.28 2nd to Details as per 10th Annexure 'D'
Middle 432 988.79 Nil 988.79 2nd to Details as per 10th. Annexure 'E'
The ld. AR submitted that as per the DVO, only 432 flats out of
the total 640 flats in projects A, B, D & E qualified for deduction u/s
80IB (10) as having built-up area of less than 1000 sq. ft. each and
the ld. CIT (A) relying on the DVO report allowed the claim of Rs.
19.28 crores out of the total claim of 29.68 crores made by the
assessee u/s 80IB (10) of the Act. However, deduction with respect to
208 flats at S.Nos. 1 to 4 in the chart above was not allowed as the
flats at S.No. 2 & 3 above, although had a built up area of less than
1000 sq. ft. as per the DVO, but the area exceeded 1000 sq. ft. when
the area open to the sky was added. The ld. AR submitted that a
balcony structure which has an equivalent structure on the top is to
be included in the built-up area but the structure which is open to the
sky does not qualify as built up area. He relied on a series of
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09
judgments of the Tribunal and Hon'ble High Courts in support of his
contention.
The Ld. AR further submitted that the flats and S.No. 1 and 4 in
the chart depicted incorrect measurements by the DVO. The Ld. AR
submitted that the deduction was denied by the Ld. CIT (A) on the
basis of measurements made by the DVO. It was submitted that the
area in respect of these 160 flats was in fact only 988.79 sq ft each
but the DVO had calculated the same at 1029.28 sq ft which was
grossly incorrect. The Ld. AR submitted that the definition of the
built-up area included inner measurements of the residential unit at
the floor level including the projections and balconies as increased by
the thickness of the wall but does not include the common areas
shared with other residential units. The Ld. AR submitted that in the
construction industry, the outer walls are 9 inches walls whereas the
internal walls are 4.50 inches. The area of the walls and the common
walls has been arbitrarily applied by the DVO thus increasing the area
by approximately 35 sq ft each. It was also submitted that the Ld. CIT
(A) did not give sufficient opportunity to the assessee to rebut the
findings of the DVO. In light of these anomalies, it was submitted, the
full claim of deduction is to be allowed to the assessee.
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09
The Ld. DR relied on the DVO’s report and the impugned order
and submitted that no interference was called for at this stage and that
the deduction claim was prima facie incorrect in view of the detailed
findings of the Assessing Officer and that even the relief allowed by the
Ld. CIT(A) deserves to be reversed.
We have heard the rival submissions and carefully perused the
relevant material placed on record. As far as ground no. 2 of the
Department’s appeal is concerned, it is seen that the issue of pro rata
deduction is covered in favour of the assessee by the following cases:-
i) ITO vs Air Developers (2009) 122 ITD 125 (Nagpur)
ii) SJR Builders vs ACIT 3 ITR (Trib) 569 (Bangalore)
iii) Sreevatsa Real Estate (P) Ltd. 9 ITR (Trib) 808
(Chennai)
In ITO vs Air Developers (supra), the Nagpur Bench held that:-
“In view of the decision of the Kolkata Bench of the Tribunal in the case of (Bengal Ambuja Housing Development Ltd. v. Dy. CIT [IT Appeal No. 1595 (Kol.) of 2005, dated 24-3-2006], which was squarely applicable to the instant case, it was to be held that if the assessee had developed a housing project wherein the majority of the residential units had a built-up area of less than 1500 sq. ft., i.e., the limit prescribed by section SO-IB(IO) and only a few residential units were exceeding the built-up area of 1500 sq. ft., there would
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09
be no justification to disallow the entire deduction under section 80-lB(10). It would be fair and reasonable to allow the deduction on a proportionate basis, i.e., on the profit derived from the construction of the residential unit which had a built-up area of less than 1500 sq. ft., i.e., the limit prescribed under section 80- IB(IO). In view of the above, the Assessing Officer was to be directed that if it was found that the built-up area of some of the residential units was exceeding 1500 sq.ft., he would allow the proportionate deduction under section 80- IB(10). Accordingly, the appeal of the revenue was to be dismissed and cross-objection of the assessee was deemed to be partly allowed. [Para 6.7]”
Similarly, in SJR Builders (supra), the Bangalore Bench of the
ITAT held that:-
“However, in the light of the decision of the Special Bench in the case of Brahma Associates v. Joint CIT [2009] 315 ITR (AT) 268 (Pune), merely because some flats are larger than 1500 sq.ft, the assessee will not lose the benefit in its entirety. Only with reference to the fats which have than the prescribed area, the assessee will lose the benefit.” The Chennai Bench of the ITAT, in the case of Sreevatsa Real
Estates (P) Ltd. (supra), held that :-
“The assessee was a company engaged in property development and claimed deduction under section 80-IB( 10). The Assessing Officer denied the claim citing various reasons, one of them being - Project was not exclusively for units with built-up area less than 1500 sq. ft. Commissioner (Appeals) confirmed the order of the Assessing Officer. In second appeal, ITAT Chennai held - Further as regards revenue's contention that since some of the housing units exceeded 1500 sq. feet., no claim under section 80-111(10) could be allowed, it was to be held that the assessee was eligible for
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09
claiming deduction under section 80-IB(10), pro rata for the housing units having area of less than 1500 sq. ft. for both the year. [Para 15]”
Keeping in view the Report of the DVO as well as the ratio of
judgments as discussed above, we concur with the finding of the
Ld. CIT(A) that the assessee was eligible to get proportionate
deduction u/s 80IB(10) of the Act in respect of flats sold during
the year on fulfilling the prescribed conditions. Hence ground no.
2 of the Department’s appeal is dismissed and the findings of the
Ld. CIT (A) are upheld.
As far as the issue of requirement of a separate approval for
each housing project is concerned (corresponding to ground no 3
of the Department’s appeal), we are of the considered opinion
that section 80IB (10) prescribes approval of a housing project. A
Housing Project may comprise of both eligible as well as ineligible
units. The deduction will be available and limited to the claim on
eligible units irrespective of the fact that the entire project
comprising of eligible and ineligible units has been approved by
the authority by way of a single approval/composite approval.
Section 80IB(10) refers to the approval of a housing project but
does not prescribe a pre-condition that the deduction will be
available in respect of only that unit or part of the project which
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09
has been separately approved by the local authority. Hence, it is
our considered view that a separate approval for each eligible
unit or project is not the intention of the Act. The Hon'ble
Madras High Court in the case of Viswas Promoters (P) Ltd. vs
ACIT 255 CTR 149 has held that the mere fact that one of the
blocks have units exceeding built-up area of 1500 sq ft per se,
would not result in nullifying the claim of the assessee for the
entire project. Consequently, it was held, that assessee was
entitled to the benefit of deduction u/s 80IB (10(c) of the Act in
respect of each of the blocks. The Pune Bench of the ITAT has
held in the case of Siddhivinayak Kohinoor Venture vs ACIT
(2014) 159 TTJ 390 that construction of even one building with
several residential projects of the prescribed size would constitute
a housing project for the purpose of section 80IB(10) of the Act.
The Pune Bench further held that each block in a particular
project has to be taken as an independent building and hence is
to be considered a housing project for the purpose of claiming
deduction u/s 80IB(10). Para 32 of the order is relevant in the
present appeal also and is being reproduced herein under for a
ready reference:-
“32. The argument of the Revenue, based on the statement of Chief Engineer, PCMC, in our view, does not
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09
help the case of the Revenue as the following discussion would show. The case set up by the Revenue is that two projects have been sanctioned by a common approval and thus the PCMC has viewed the two projects as a single composite project. It is contended by the Revenue that the expression 'housing project', though not defined in s. 80-113(10) of the Act, should be taken to be the project per se, as approved by a 'local authority' for the purposes of s. 80-IB( 10) of the Act. No doubt, for a 'housing project' to be eligible for deduction under s. 80-IB (10) of the Act, it is required to be approved by a 'local authority', so however, the phraseology of s. 80-IB (10) of the Act does not reflect a legislative intent that the project should be 'as approved' by a 'local authority'. The requirement of s. 80-IB (10) of the Act to the effect that project should be approved by a 'local authority' is fulfilled no sooner when the 'housing project' considered by an assessee is approved by a 'local authority'. Moreover, the expression 'housing project' is not defined in the Development Control Rules for PCMC i.e. the 'local authority' in the case before us and thus, the said enactment cannot be resorted to for the purpose of understanding the meaning of expression 'housing project' contained in s. 80-IB(10) of the Act. Therefore, so long as the claim of deduction is in relation to a 'housing project', which has been approved by the 'local authority', it would satisfy the requirement of s. 80- IB(10) of the Act. Pertinently, if the proposition of the Revenue is to be upheld, the same would be quite contrary to the manner in which the expression 'housing project' contained in s. 80-IB (10) of the Act has been understood by the Hon'ble Bombay High Court in the case of Vandana Properties (supra) and also by the Hon'ble Madras High Court in Viswas Promoters (P.) Ltd. (supra) and Arun Excello Foundations (P.) Ltd. (supra). It may also be pertinent to observe that the Hon'ble Bombay High Court in Vandana Properties (supra) not only noted that the expression 'housing project' is not defined under s. 80-IB(10) of the Act but also noted that the same was not defined even under the relevant local regulations before it, viz. the Mumbai Municipal Corporation Act, 1988 and the Development Control Regulations for Greater Mumbai, 1991. Thus, the Hon'ble High Court proceeded to observe that the expression 'housing project' in s. 80-IB(10) would have to be construed as commonly understood. Even in the case before us, there is no dispute that the expression 'housing project' is not defined in the Development Control Rules for PCMC and therefore, the concept of'housing project’ as sought to be understood by the AO
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09
based on the explanation of Chief Engineer. PCMC is not relevant for the purposes of s, 80IB (I0) of the Act. Thus, the argument of the Revenue to the effect that since SWRH and ’S'1 projects have been approved by PCMC under a common approval, the two projects should be combined and considered as a single project for the purpose of s. under s. 80-IB( 10) of the Act in our opinion is misplaced.” 35. Therefore, in view of the facts of the case as well as the
judicial precedents discussed above, we dismiss ground no. 3 of
the Department’s appeal. Ground nos. 4 & 5 of the Department’s
appeal being general in nature are not being adjudicated upon
and are dismissed. In the result, the appeal of the department is
dismissed.
As far as ground nos. 1 & 2 of the assessee’s appeal are
concerned, the first issue requiring adjudication is whether the
projections open to sky are to be included or excluded in the
calculation of the built-up area of a particulars residential unit.
We find that this issue is covered in favour of the assessee by the
decision of the ITAT Pune Bench in the case of Naresh T.
Wadhwani vs DCIT (52 taxmann.com 360 Pune-Trib) wherein, in
para 27, the Bench has held as follows:-
“ 27. Considered in the above background, we conclude by holding that the Assessing Officer and thereafter the CIT(A) has erred in including the area of projected terrace (open to sky) for the purposes of computing 'built- up area' while examining the condition prescribed in
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09
clause (e) of section 80IB( 10) of the Act. Once the area of projected terrace (open to sky) is excluded then there is no dispute that the residual built-up area of six units in question falls within the prescribed limit of 1500 sq.ft. As a result, we hold that assessee fulfills the condition prescribed in clause (c) of section 80IB (10) of the Act with regard to the six units in question. Therefore, we set-aside the order of the CIT(A) and direct the Assessing Officer to consider that the six units in question fulfill the condition prescribed in clause (e) of section 80I B(10) of the Act and the assessee is entitled to the benefit of section 80IB(10) of the Act.”
In the proceedings before us, the Department could not point
out any judgment/judicial precedent to the contrary. We
accordingly hold that the balconies open to the sky are to be
excluded from the calculation of the built-up area of a particular
residential unit. We, therefore, direct that the assessee be
allowed the claim of deduction u/s 80IB (10) in respect of flats (at
S.Nos. 2 & 3 as in the chart reproduced in on Para 28 of this
order) which have been excluded from the benefit of deduction by
including the balconies open to sky for the purpose of calculating
the built-up area of the individual units.
The only issue remaining for adjudication after this is the
claim of the assessee challenging the measurements of the DVO
in respect of flats at Sl. no. 1 & 4 of the chart (Para 28 of this
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09
order). It is the assessee’s contention that the correct
measurement is 988.79 sq ft whereas the DVO has calculated the
build up area at 1029.28 sq. ft. It is also the assessee’s plea that
it had not been afforded a proper opportunity to explain the
discrepancy before the Ld. CIT (A). Hence in the interest of
justice, we deem it proper to restore this limited issue of
discrepancy in measurement, as claimed by the assessee, to the
file of the Assessing Officer for fresh examination and
adjudication thereon after giving due opportunity to the assessee
to present its case. In the result, the appeal of the assessee is
partly allowed.
In the final result, both the appeals of the department are
dismissed, the C.O. of the assessee is allowed and the appeal of
the assessee is partly allowed.
Order pronounced in the Open Court on 30th May, 2016.
Sd/- Sd/- (G.D. AGRAWAL) (SUDHANSHU SRIVASTAVA) VICE PRESIDENT JUDICIAL MEMBER
Dated: the 30th May, 2016 ‘GS’
I.T.A. Nos. 5614, 1950, 5849/D/2012, CO 20/D/15 Assessment Years: 2009-10, 2008-09