No AI summary yet for this case.
Income Tax Appellate Tribunal, INDORE BENCH, INDORE
Before: SHRI C.M. GARG & SHRI O.P. MEENA
आदेश /O R D E R
PER SHRI C.M. GARG, JM
This appeal has been filed by the Revenue-appellant against
the order of the learned CIT(A), Raipur, Camp at Bhopal dated
22.3.2013 in First Appeal No. 211/10-11 for the assessment year
2006-07 on the following grounds :- 1
ITO vs. M/s Global Housing ITA No. 525/Ind/2913 “On the facts and in the circumstances of the case, the CIT(A) has erred in :-
1 deleting the disallowance of Rs.43,29,927/- made by the A.O. u/s 80IB(10) of IT Act, 1961.
allowing the claim of deduction u/s 80IB(10) of the Aeven though the assessee acted in the capacity of contractor and did not own the land and no colonizer licence was obtained by the assessee
allowing the claim of deduction u/s 80IB(10) of the Act even though the building completion certificate has not been obtained from the competent authority which is mandatory in terms of Explanation (ii) to sub-clause (iii) of clause (a) of section 80IB(10).”
Before us, the learned DR submitted that since the assessee
has acted in the capacity of contractor and did not even own the
land as also the colonizer licence was not obtained by it, the
assessee was not at all entitled to the claim u/s 80IB(10) of the Act.
He further submitted that in terms of Explanation (ii) to sub-clause
(iii) of clause (a) of section 80IB(10) of the Act, it is mandatory for
the assessee to obtain building completion certificate for claiming
the deduction u/s 80IB(10) of the Act, which condition the assessee
has failed to comply. He, therefore, prayed that since the assessee
has not complied with the mandatory provisions of the Income Tax
Act, 1961, the Commissioner of Income Tax (Appeals) was totally
ITO vs. M/s Global Housing ITA No. 525/Ind/2913 unjustified in allowing the claim of the assessee against the very
spirit of the Act.
Replying to the above, besides other relevant arguments, the
learned counsel for the assessee submitted that as per section 301
of the M.P. Municipal Corporation Act, there is no provision of
issuing completion certificate by the Municipal Corporation.
Therefore, the requirement of the same cannot be imposed and
enforced upon the assessee by the Income Tax Act, 1961. However,
he fairly accepted that the issue in the present appeal has been
decided against the assessee by the Hon'ble jurisdictional High
Court in the case of CIT vs. M/s Global Reality; ITA No. 40/2012.
We have carefully considered the facts of the case, orders of
the authorities below and the arguments of the respective parties.
So far as the deduction u/s 80IB(10) of the Act is concerned,
we find that in a recent judgment, the Hon'ble jurisdictional High
Court of Madhya Pradesh in the case of CIT vs. M/s Global Reality;
ITA No. 40/2012 and others has decided the issue against the
assessee by holding as under :-
ITO vs. M/s Global Housing ITA No. 525/Ind/2913 19. The provision such as clause (a) as amended, sensu
stricto, cannot be considered as a new condition and that too
incapable of compliance. Inasmuch as, clause (a) deals with
the time frame within which the housing project was
expected to be completed, to get the benefit of the prescribed
deduction. Notably, the amended Section 80IB (10) (a)
extends the benefit even to the housing projects approved by
the Local Authority before 31.03.2007, instead of
31.03.2005 - as was provided in the unamended provision.
Therefore, necessity was felt to make distinction between
the two classes of housing projects for specifying the time
frame for completion. The one approved by the Local
Authority before 1st day of April, 2004; and the other class
of housing project approved by the Local Authority on or
after 1st April 2004 till 31.03.2007. In either case, the time
frame for completion of project has been prescribed as four
years. In that, the project approved before 1st April, 2004
has been given time to complete before 31.03.2008; and in
the latter category I.T.A.Nos.40/2012, 36/2012 &
35/2012 within four years from the end of the financial 4
ITO vs. M/s Global Housing ITA No. 525/Ind/2913 year in which the housing project was approved by the Local
Authority.
Thus understood, similar time frame for completion of
housing project has been given to both class of housing
projects. Moreover, the explanation below clause (a), in
particular (ii), applies to both class of housing projects
uniformly. It postulates that "the date of completion of
construction of housing project" shall be taken to be "the date
on which completion certificate" in respect of such housing
project "is issued by the Local Authority". If Explanation (ii) is
superimposed on the expression "completes such
construction" in Clause (a) of Section 80IB(10), it would
mean that the housing projects commenced on or after
01.10.1998 must possess completion certificate issued by
the Local Authority on or before the cut off date, as may be
applicable - to become eligible for tax deduction. As per
Explanation (ii), therefore, the synonym of "completes such
construction" would be the date on which completion
certificate is issued by the Local Authority. No more and no
ITO vs. M/s Global Housing ITA No. 525/Ind/2913 less. Thus, enough indication and also sufficient time has
I.T.A.Nos.40/2012, 36/2012 & 35/2012 been given to both
the class of housing projects to fulfill that condition. The
provision is in the nature of limiting the benefit of deduction
to the specified housing projects, and not to those who fail to
fulfill the requirement of completion of construction in time
frame specified for the respective category of housing
projects. This has been done in larger public interest - to
ensure that the benefit is given only to such projects who
would further the goal of providing low cost economic houses
to the deserving persons in reasonable time.
Concededly, it is within the domain of Parliament to
extend benefit or privilege to certain class of persons and
also to withdraw the same for just reasons. That cannot be
questioned, unless shown to be unconstitutional in form or
its substance. It was thus open to the Parliament, to provide
for a cut off date for completion of the housing projects, as a
condition precedent to avail benefit of deduction. In the past,
such stipulation was in place, but, later on, it was done
ITO vs. M/s Global Housing ITA No. 525/Ind/2913 away with. However, by amendment which came into effect
from 1st April, 2005, the condition for completion of project
within specified time has I.T.A.Nos.40/2012, 36/2012 &
35/2012 been reintroduced, while giving sufficient time
(four years) to the assessee to comply for being entitled to
get deduction.
A priori, it is not a case of imposing new condition, much
less, with retrospective effect as has been argued before us;
unlike introduction of new condition in the shape of clause
(d) - which obviously could be applied only prospectively, as
held by the Supreme Court in the aforesaid decisions.
Clause (a) stands on a completely different pedestal. It
cannot be treated as a new condition linked to the approval
and construction or having retrospective effect as such. For,
it gives at least four years' time frame to both class of
housing projects; to wit, housing projects approved prior to
1st April, 2004 or after 1st April, 2004. The four years period
obviously has prospective effect, albeit limiting the period for
completion of the project, to avail of the benefit. Four years'
ITO vs. M/s Global Housing ITA No. 525/Ind/2913 time frame for completion of the project, by no standards,
can be said to be unreasonable, harsh, absurd or incapable
of compliance. It is also not a case of withdrawal of vested
right of the developer, as such. No developer can claim
vested right to complete the housing project
I.T.A.Nos.40/2012, 36/2012 & 35/2012 in indefinite
period. The right arising from Section 80IB, is coupled with
the obligation or duty to complete the project in specified time
frame. If the developer does not complete the housing project
within specified time, will not receive that benefit. There is
no compulsion on him to complete the project in four years.
Notably, even the approvals to the construction of housing
project granted by the Local Authority specify the date
within which the construction must be completed, as per the
time frame specified in the permission. If the project is not
completed within the stipulated time, the developer is free to
get that period renewed or extended from the Local Authority
as per the applicable Rules and Regulations. The provision
for claiming tax deduction from profits, can certainly
ITO vs. M/s Global Housing ITA No. 525/Ind/2913 prescribe for reasonable conditions and more so time frame
for completion of the project, in larger public interest.
Suffice it to observe that, no comparison can be drawn
between the new condition prescribed in terms of clause (d)
and that of clause (a). Condition in Clause (a), neither
operates retrospectively nor can be said to be absurd, unjust
or expecting I.T.A.Nos.40/2012, 36/2012 & 35/2012 the
assessee to comply with something which is impossible to
achieve.
The next question that needs to be answered, is,
whether the stipulation in Section 80IB(10)(a) can be said
to be directory. Considering the prodigious benefit offered in
terms of Section 80IB to the assessee (hundred per cent of
the profits derived in any previous year relevant to any
assessment year); and the purpose underlying the same -
which is inter alia burden on the public exchequer due to
waiver of commensurate revenue - the stipulation for
obtaining completion certificate from the Local Authority
before the cut off date, must be construed as mandatory.
ITO vs. M/s Global Housing ITA No. 525/Ind/2913 The fact that compliance of that condition is dependent on
the manner in which the proposal is processed by the Local
Authority, the provision cannot be construed as a directory
requirement. It is a substantive provision mandating
issuance or grant of completion certificate by the Local
Authority before the cut off date or specified time, as a
precondition to get the benefit of tax deduction. Else, it will
then be open to the assessee to rely on other circumstances
or I.T.A. Nos. 40/2012, 36/2012 & 35/ 2012 evidence to
plead that the housing project is complete - requiring enquiry
into those matters by the Tax Authorities - sans a completion
certificate issued by the Local Authority in that behalf. A
priori, the argument of substantial compliance is sufficient,
would lead to uncertainty about the date of completion of the
project which is the hallmark for availing of the benefit of tax
deduction. Only with this intent the legislature in its wisdom
has predicated that, "the completion of construction" of the
housing project is taken to be "the date on which" the
completion certificate "is issued" by the Local Authority. To
interpret it to include an ex post facto certificate or such 10
ITO vs. M/s Global Housing ITA No. 525/Ind/2913
certificate issued by the Local Authority after the cut off
date, would not only result in rewriting of the express
provision and run contrary to the unambiguous position
pronounced in the Section, but also doing violence to the
legislative intent. For, Explanation (ii) will then have to be
read as "date of completion of construction of the housing
project shall be taken to be the date as certified by the Local
Authority in that behalf", irrespective of the date of issuance
of such certificate by the I.T.A.Nos.40/2012, 36/2012 &
35/2012 Local Authority. Indeed, in a given case if the
assessee is able to substantiate that the completion
certificate "was in fact issued" by the Local Authority before
the cut off date, but could not be produced by him within
time due to reasons beyond his control, the argument of
substantial compliance of the provision can be tested. Any
other interpretation would result not only in uncertainty (in
finalization of assessment proceedings due to non-issuance
or delayed issuance of such certificate by the Local Authority
ITO vs. M/s Global Housing ITA No. 525/Ind/2913
and prone to manipulations at the end of the Local
Authority); but also have to yield to the subjective
satisfaction of the Assessing Authority and of investing wide
discretion in that Authority, which, eventually, may only end
up in getting embroiled in litigation. If the assessee has
failed to comply with the condition of obtaining completion
certificate from the Local Authority before the cut off date, he
must take the consequence therefor and of denial of the
benefit of tax deduction offered to him on that count.
We cannot be oblivious of the fact that the Municipal
Laws of different States are not uniform in respect of
procedure for I.T.A.Nos.40/2012, 36/2012 &
35/2012 issuance of completion certificate. To wit, in some
States, the dispensation provided is to issue partial or full
occupation certificate; and thereafter issue completion
certificate after removal of all the deficiencies pointed out by
the Local Authority. In some States, the Municipal Law may
provide for issuing partial or full completion certificate. The
ITO vs. M/s Global Housing ITA No. 525/Ind/2913
requirement of completion certificate issued by the Local
Authority, as envisaged in Section 80IB(10)(a) of the Income
Tax Act, which is a Central enactment dealing with the
special subject of taxation, however, is, of only one
certificate - which is full completion certificate issued by the
Local Authority before the cut off date. That is to lend
credence to the factum of completion of the entire housing
project in all respects as per the approval granted by the
Local Authority. It can be safely assumed that the legislature
was conscious of this position, for which, express provision
has been made as to the meaning of the date of completion
of the housing project linked to the "date on which"
completion certificate "is issued" by the "Local Authority", as
predicated in Explanation (ii) thereunder.
“26. We accordingly hold that issuance of completion
certificate, after the cut off date by the Local Authority but,
mentioning the date of completion of project before the cut off
date does not fulfill the condition specified in clause (a) of
ITO vs. M/s Global Housing ITA No. 525/Ind/2913
Section 80IB (10) read with Explanation (ii) thereunder. We
reject the argument of the assessee that the effect of
amended clause (a) of sub-Section 10 of Section 80IB, which
has come into force with effect from 1st April, 2005 ,has
retrospective effect or that it is unjust in any manner or
incapable of compliance at all. Similarly, the requirement of
securing completion certificate issued by the Local Authority
before the cut off date is not directory, in view of the express
provision in Section 80IB(10)(a) and the Explanation (ii)
thereunder. The completion certificate granted by the Local
Authority must bear the date of having been issued before
the cut off date.
That takes us to the argument of the assessee that
the stipulation in Section 80IB(10)(a) of completion
certificate issued by the Local Authority before the cut off
date, cannot be applied in the case of assessee following
the work in progress accounting method. In our opinion, the
provision in the form of Section 80IB (10)(a), applies
uniformly to all the assessees - be it following work in 14
ITO vs. M/s Global Housing ITA No. 525/Ind/2913
progress accounting method or otherwise. The benefit of
deduction under this provision can be availed by the
assessee following the work in progress accounting
method, provided he has complied with the stipulation of
having produced completion certificate issued by the Local
Authority before the cut off date, as may be applicable in
his case. In other words, if the housing project was
approved by the Local Authority before 1st April, 2004, he
must submit completion certificate issued by the Authority
having been issued before the 31st March, 2008. Whereas,
in the case of housing project approved on or after 1st April,
2004, the assessee can avail of the benefit provided
completion certificate issued by the Local Authority is
within four years from the end of the financial year in
which the concerned housing project was approved by the
Local Authority. If this condition is not fulfilled, the
assessee who maintains work in progress accounting
method and has claimed deduction under Section
ITO vs. M/s Global Housing ITA No. 525/Ind/2913
80IB(10)(a) must suffer the consequence of disallowance or
withdrawal of the benefit claimed by him on that count.
Accordingly, these appeals succeed. The impugned
judgment of the Tribunal is set aside; and in the facts of
the present case, the decision of the Assessing Officer to
disallow deduction under Section 80IB(10)(a) of the Income
Tax Act is upheld. No order as to costs.”
The Hon'ble jurisdictional High Court has considered the
sweep of amended clause (a) of the provision under sub-section (10)
of section 80IB of the Act and held that the provisions of clause (a),
as amended, sen sustricto cannot be considered as new condition
and that too incapable of compliance. The clause deals with the
time frame within which the housing project was expected to be
completed to get the benefit of prescribed deduction. The Hon'ble
High Court has held that issuance of completion certificate after the
cut off date by the local authority but mentioning in the date of the
completion of project before cut off date, does not fulfil the
condition specified in clause (a) of section 80IB(10) read with
Explanation 2 thereunder. In view of this finding of the Hon'ble 16
ITO vs. M/s Global Housing ITA No. 525/Ind/2913 jurisdictional High Court, we find force in the appeal of the Revenue
and allow the same.
In the result, the appeal of the revenue stands allowed.
The order has been pronounced in open Court on 2nd May,
2017.
Sd/- sd/-
लेखा सद�य �या�यक सद�य (O.P.Meena) (C.M. Garg) Accountant Member Judicial Member
May 2, 2017.
Dn/