NAGESH MOTIBAI DESAI,MUMBAI vs. ITO, WARD, 42(1)(3), MUMBAI
What did the Tribunal hold?
The Tribunal held that the delay of 141 days in filing the appeal before the CIT(A) was unintentional and due to sufficient cause, specifically attributing it to issues with the assessee's counsel. The Tribunal noted that the CIT(A) dismissed the appeal without affording an opportunity to the assessee to explain the delay, which violates principles of natural justice and deprives the assessee of a substantive right. Relying on the Supreme Court's decision in Collector, Land Acquisition v Mst. Katiji And Others, the Tribunal condoned the delay and set aside the appellate order. Furthermore, the Tribunal observed that the appellate order was passed without proper adjudication on merits as the assessee had not submitted relevant documents. Therefore, in the interest of justice and fair play, the Tribunal remanded the entire matter back to the CIT(A) for fresh adjudication on merits, granting the assessee a final opportunity to advance arguments, submit additional evidence, and raise additional grounds. The issues of disallowance of cost of acquisition, validity of reopening notice, and the section under which the 148A(d) order was passed were not decided on merits by the ITAT, as the case was remanded.
What were the facts?
The assessee, Nagesh Motibhai Desai, filed an appeal before the ITAT against an order of the CIT(A) dated 30.08.2024. The CIT(A)'s order was in relation to an assessment order passed by the Income Tax Officer, Ward-42(1)(3) under section 147 r.w.s. 144B of the Income-tax Act, 1961, for Assessment Year 2017-18. The appeal before the CIT(A) was dismissed in limine due to a delay of 141 days in filing, without adjudication on merits. The assessee had not provided reasons for the delay before the CIT(A), and the case was listed for hearing five times without response. The assessee's appeal to the ITAT challenges this dismissal and also raises additional grounds related to the reopening notice and the order under section 148A(d).
What were the issues?
1. Whether there was sufficient cause for condoning the delay of 141 days in filing the appeal before the CIT(A), and whether the CIT(A) erred in dismissing the appeal without considering the merits. - Assessee's contention: The delay was due to non-communication by the assessee's counsel, a strained relationship with the counsel, and discontinuation of services. The assessee claims the delay was unintentional and bonafide, and requests condonation. - Revenue's contention: Not recorded in the judgment. 2. Whether the Assessing Officer erred in disallowing the Cost of Acquisition amounting to Rs.89,86,562/- in the absence of supporting documents. - Assessee's contention: Request to allow the cost of acquisition. - Revenue's contention: Not recorded in the judgment. 3. Whether the reopening notice was issued beyond three years, requiring approval from the Principal Chief Commissioner or equivalent authorities as per amended section 151, and if approval taken from PCIT was valid. - Assessee's contention: Approval for reopening beyond three years was taken from PCIT, which is not the prescribed authority under amended section 151. - Revenue's contention: Not recorded in the judgment. 4. Whether the Assessing Officer failed to mention the specific section under which the order u/s 148A(d) was passed, i.e., whether it was under section 149(1)(a) or 149(1)(b). - Assessee's contention: The AO did not specify the section under which the order u/s 148A(d) was passed. - Revenue's contention: Not recorded in the judgment.
Which sections of the Income-tax Act were involved?
Section 147,Section 144B,Section 151,Section 148A,Section 149
AI-generated summary — verify with the full judgment below
Cases cited in this judgment(1)Show listHide list
Detected automatically from the text. Citations are also linked where they appear in the judgment. The count shows how many other judgments on BharatTax rely on the same authority.
- Collector, Land Acquisition v. Mst. Katiji3,926 citing167 ITR 471 · 1987 · SC
Before: SHRI SANDEEP GOSAIN & SHRI PRABHASH SHANKAR
PER PRABHASH SHANKAR [A.M.] :- The present appeal arising from the appellate order dated 30.08.2024 is filed by the assessee against the order passed by the Learned Commissioner of Income-tax (Appeals)/National Faceless Appeal Centre, Delhi [hereinafter referred to as “CIT(A)”] pertaining to the assessment order passed u/s.147 r.w.s.144B of the Income-tax Act, 1961 [hereinafter referred to as “Act"] dated 26.04.2023 for the Assessment Year [A.Y.] 2017-18. Page 2 Nagesh Motibhai Desai
The grounds of the appeal are as under:-
On the Facts and in the circumstances of the case and in law, the ld.CIT(A) has erred in dismissing the appeal that based on that there is no sufficient cause for condoning the delay (141Days) in the institution of appeal by the appellant as no reason has been filed for the delay. Therefore, the case is not being dealt with and examined on merits.
On the Facts and in the circumstances of the case and in law, the ld. AO has erred in disallowing Cost of Acquisition amounting to Rs.89,86,562/- in absence of supporting documents. Requesting Your Honor, to allow the cost of acquisition.
All the Grounds of Appeal are without prejudice to each other. Additional grounds of Appeal 1. “On the Facts & Circumstances of the case, the Ld. Assessing Officer-ITO WARD 42(1)(3), hereinafter referred to as the Ld.. A.O. has failed to appreciate that the AO issued reopening Notice beyond period of three years, approval was required. to be taken as per the provisions of amended section 151 of the Act from Principal Chief Commissioner or Principal Director General or Chief Commissioner or Director General however approval is taken from PCІТ”. 2. “On the Facts & Circumstances of the case, the Ld. Assessing Officer- ITO WARD 42(1)(3), hereinafter referred to as the ld. A.O. has failed to mention the section under which the Order u/s 148A(d) has been passed i.e the Ld. AO has not specified whether Order has been passed u/s 149(1)(a) or 149(1)(b)”.
Brief facts of the case are that the assessee is an Individual in whose case, the AO made addition of Rs.79,86,562/- disallowing cost of acquisition based in the absence of supporting documents. Being aggrieved, the assessee filed an appeal before the ld. CIT(A) for the said order. There was a delay in filing in appeal of 141 days for which the assessee did not provide any reasons for the same. The appellate authority did not adjudicate the appeal on merits. It is also noticed from the appellate order that the case was fixed for hearing on as many as five Page 3 Nagesh Motibhai Desai times but they did not elicit any response from the assessee. In the light of these facts, the CIT(A) observed that the assessee was negligent and no sufficient cause was attributed for the delay as well. Accordingly, he dismissed the appeal in limine without considering merits of the case.
Before us, the ld.AR has filed an affidavit stating the reasons for the delay mainly attributing to non-communication by the Counsel of the assessee regarding receipt of assessment order in time. It is stated that the relationship of the assessee with the counsel is strained and his services have also been discontinued. It is submitted that as soon as the assessment order was conveyed to him, he immediately filed the appeal. It is requested to condone the delay.
We find that the delay in filing of appeal though had been attributed to the Counsel before us, there was no submission made in this regard before the appellate authority. Besides, no reasons have been stated in respect of repeated non-compliance before the ld.CIT(A) during appeal proceedings. The assessee before us has also filed additional ground of appeal not raised before the appellate authority.
On careful consideration of the submissions of the assessee, we are of the considered opinion that the delay in filing of the present appeal was not intentional but due to unavoidable and sufficient cause. Page 4 Nagesh Motibhai Desai Such a bonafide mistake should have been condoned. Moreover, the ld.CIT(A) is also not justified in dismissing the appeal on the ground of delay without affording any opportunity to the assessee to explain it which is against the principles of natural justice and also amounts to taking away a substantive right of the assessee. In this connection, reliance could be placed on the landmark decision of hon'ble Supreme Court which inter alia held in Collector, Land Acquisition v Mst. Katiji And Others- 167 ITR 471 (SC) that “ordinarily, a litigant does not stand to benefit by lodging an appeal late........Refusing to codone delay can result in a meritorious matter being thrown out at the very threshold and cause of justice being defeated....Any appeal or any application, other than an application under any of the provisions of Order XXI of the Code of Civil Procedure, 1908, may be admitted after the prescribed period if the appellant or the applicant satisfies the court that he had sufficient cause for not preferring the appeal or making the application within such period.... A litigant does not stand to benefit by resorting to delay. In fact, he runs serious risk.” We therefore, condone the delay setting aside the appellate order.
We have duly perused the records from which it is noticed that in this case, the appellate order was passed without proper adjudication on merits of the case as the assessee did not submit relevant documents and evidences in support of the issues involved before the appellate authority. We are of the considered view in the interest of justice and fairplay, the entire matter needs to be properly adjudicated by the ld.CIT(A).As such, we are granting a final opportunity to the assessee to advance his arguments/submissions before the him so as to provide details in connection with the merits of the case and additional evidences, if any to support his contentions. The assessee is also granted liberty to raise any additional ground as well. Accordingly, in the substantial interest of justice, we set aside the appellate order and remand all the issues to the ld.CIT(A) for passing the appellate order afresh after allowing adequate opportunity of hearing to the assessee.
In the result, the appeal is allowed for statistical purposes. Order pronounced in the open court on 13/10/2025. SANDEEP GOSAIN (न्यायिक सदस्य /JUDICIAL MEMBER) Place: मुंबई/Mumbai दिनांक / Date 13.10.2025 Lubhna Shaikh / Steno PRABHASH SHANKAR (लेखाकार सदस्य/ACCOUNTANT MEMBER) Page 6 Nagesh Motibhai Desai आदेश की प्रतिलिपि अग्रेषित/
More judgments on Section 147
- ACIT Central Bilaspur, Bilaspur vs Arun Kumar Agrawal, SaktiITSSA 26/RPR/2025[2018-19]Status: Disposed21 Oct 2026AY 2018-19
- Vinod Agrawal, Kawardha vs Assisstant Commissioner of Income Tax…ITA 666/RPR/2026[2019-20]Status: Heard21 Oct 2026AY 2019-20
- Sar Business Tradelink Private Limited… vs Income Tax Officer, Ward - 1(2), RaipurITA 599/RPR/2026[2014-15]Status: Heard21 Oct 2026AY 2014-15
- Tarunaben Maganlal Bhut, Navagam vs ITO Ward 2(2)(1), RajkotITA 673/RJT/2026[2024-25]Status: Disposed21 Oct 2026AY 2024-25
- Neo Incorporation, Rajkot vs DCIT Circle- 1(2), RajkotITA 471/RJT/2026[2012-2013]Status: Disposed21 Oct 2026AY 2012-2013
Recent GST High Court judgments
Search GST case law →- Akshaya Consortium vs. The Assistant Commissioner (St)Andhra Pradesh · 28 Oct 2026
- Dipanshu Aggarwal vs. Director General Of GST IntelligenceDelhi · 28 Oct 2026
- Dezinetree Projects PVT. LTD. vs. Spokes Digital Inc And AnrDelhi · 28 Oct 2026
- Jaydeep Jayantilal Hudaka vs. State Of GujaratGujarat · 28 Oct 2026
- Commissioner/Additional Commissioner Of Central Tax vs. M/S INDIA Agro Exports Private LimitedKarnataka · 28 Oct 2026